THE STATE OF BIHAR vs PAWAN KUMAR
THE STATE OF BIHAR vs PAWAN KUMAR - Supreme Court Case 2022
NONREPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
I.A. Nos. 154740154741 of 2021, 153531153532 of
2021, 165173 of 2021, 160138 of 2021, 160139 of 2021,
160142 of 2021 and 163177 of 2021
IN
CIVIL APPEAL NOS.36613662 OF 2020
THE STATE OF BIHAR AND OTHERS ...APPELLANT(S)
VERSUS
PAWAN KUMAR AND OTHERS ...RESPONDENT(S)
O R D E R
1. All these I.As arise out of the directions issued by this
Court vide order dated 10th November 2021 in Civil Appeal
Nos. 36613662 of 2020.
2. The State of Bihar had approached this Court
challenging the order dated 14th October 2020, passed by the
National Green Tribunal, Principal Bench, New Delhi
1
(hereinafter referred to as “the Tribunal”) in O.A. No.
40/2020/EZ with O.A. No. 57/2020/EZ, thereby issuing
various directions. This Court after taking into consideration
various aspects, including the necessity to curb illegal
mining activities and the necessity to permit legal mining in
the interregnum till the other directions issued by this Court
are complied with, had issued the following directions dated
10th November 2021:
“14. We therefore find it appropriate to substitute
the directions issued by the Tribunal vide judgment
and order dated 14th October 2020, with the
following directions:
(i) The exercise of preparation of DSR for
the purpose of mining in the State of Bihar
in all the districts shall be undertaken
afresh. The draft DSRs shall be prepared by
the subdivisional committees consisting of
the SubDivisional Magistrate, Officers from
Irrigation Department, State Pollution
Control Board or Committee, Forest
Department, Geological or mining officer.
The same shall be prepared by undertaking
site visits and also by using modern
technology. The said draft DSRs shall be
prepared within a period of 6 weeks from
the date of this order. After the draft DSRs
2
are prepared, the District Magistrate of the
concerned District shall forward the same
for examination and evaluation by the
SEAC. The same shall be examined by the
SEAC within a period of 6 weeks and its
report shall be forwarded to the SEIAA
within the aforesaid period of 6 weeks from
the receipt of it. The SEIAA will thereafter
consider the grant of approval to such DSRs
within a period of 6 weeks from the receipt
thereon;
(ii) Needless to state that while preparing
DSRs and the appraisal thereof by SEAC
and SEIAA, it should be ensured that a
strict adherence to the procedure and
parameters laid down in the policy of
January 2020 should be followed;
(iii) Until further orders, we permit the
State Government to carry on mining
activities through Bihar State Mining
Corporation for which it may employ the
services of the contractors. However, while
doing so, the State Government shall ensure
that all environmental concerns are taken
care of and no damage is caused to the
environment.”
The matter was directed to be listed after 20 weeks.
I.A. Nos. 154740154741 of 2021
3
3. The present I.As have been filed being aggrieved by the
cancellation of Letter of Intent (hereinafter referred to as the
“LoI”) dated 21st January 2020, issued in favour of the
applicant. The applicant also apprehended that in view of the
order dated 10th November 2021 passed by this Court with
respect to Banka District, the State Government may also
issue short Notice Inviting Tender (hereinafter referred to as
the “NIT”) with respect to Kishanganj District. After the
present I.As were filed, NIT has also been issued in respect of
sand ghats in Kishanganj District on 2nd December 2021.
4. Shri Mukul Rohatgi, learned Senior Counsel appearing
on behalf of the applicant submitted that the applicant was a
successful bidder in the auction held for the Kishanganj
District and as such, the action of the respondent in
cancelling the LoI and issuing fresh NIT for Kishanganj
District is not sustainable in law. It is submitted that the
offer of the applicant was for a much higher amount as
compared to the offer received by the respondentBihar State
Mining Corporation (hereinafter referred to as the
“Corporation”) for Kishanganj District. He therefore
4
submitted that it is in the interest of justice that the
applicant may be permitted to carry out the mining activities
in the Kishanganj District.
I.A. Nos. 153531153532 of 2021
5. In the present I.As, the applicant claimed that it was a
successful bidder for auction of sand ghats in respect of
Banka District for the period from 2015 to 2019. It is the
case of the applicant that it had been granted extension after
the year 2019 from time to time and the last of such
extensions was granted till 31st March 2022. The applicant
apprehended that in pursuance to the order dated 10th
November 2021 passed by this Court, NIT would also be
issued in respect of Banka District. During the pendency of
these I.As, NIT in respect of sand ghats in Banka District has
been issued by the Corporation on 2nd December 2021.
6. We have heard Shri Narender Hooda, learned Senior
Counsel appearing on behalf of the applicant in the said
application.
7. Shri Hooda submitted that since the applicant was the
highest bidder in the auction conducted for the period from
5
2015 to 2019 and since thereafter, the applicant had been
granted extensions, he is entitled to carry out the mining
activities at least till 31st March 2022. He further submitted
that the amount which the respondentCorporation would
receive for the sand ghats in pursuance to the NIT dated 2nd
December 2021, is much less than the one the applicant has
offered and therefore, it is in the interest of justice that the
applicant be permitted to continue with the mining activities
at least till 31st March 2022.
I.A. No. 165173 of 2021
8. The grievance of the present applicant is somewhat
similar to the grievance of the applicant in I.A. Nos. 154740
154741 of 2021. Here again, it is the contention of the
applicant that it was a successful bidder in respect of the
sand ghats in the Jamui District in the bids conducted in the
year 2019. It is therefore submitted that the impugned NIT
dated 15th November 2021 issued by the Corporation
prejudicially affects the interest of the applicant.
9. We have heard Shri Prashant Bhushan, learned counsel
in support of the said application. Shri Bhushan submitted
6
that the applicant was a successful bidder in the bids
conducted in the year 2019 and he is entitled to be appointed
as a contractor or in the alternative at least he be granted a
right to match the highest bidder along with the right of first
refusal.
I.A. Nos. 160138, 160139 and 160142 of 2021
10. The grievance of the present applicant is similar to the
grievance of the applicant in I.A. Nos. 153531153532 of
2021. It is the case of the applicant that it was a successful
bidder for the period from 2015 to 2019 at Nawada District.
Thereafter, the applicant was granted extensions from time to
time and the last of such extensions was granted till 31st
March 2022.
11. Shri C.A. Sundaram, learned Senior Counsel appearing
on behalf of the applicant submitted that as such, the
applicant would be entitled to carry out the mining activities
till 31st March 2022.
I.A. No. 163177 of 2021.
7
12. In the present application, it has been submitted on
behalf of the applicant that the mining activities which are
being carried out by the Corporation are without the grant of
Environmental Clearance. It is submitted that the very
purpose for which the order was passed by the Tribunal and
modified by this Court, was to ensure that the environment
is not damaged on account of rampant mining activities
without the grant of Environmental Clearance by the
Competent Authority. It is therefore submitted that the NITs
dated 15th November 2021 and 2nd December 2021 are silent
about the environmental aspects and therefore, the action of
the respondentCorporation in issuing NITs amounts to
contempt of this Court.
13. Shri Atmaram Nadkarni, learned Senior Counsel
appearing on behalf of the appellantState of Bihar submitted
that the NITs in question were issued for a limited period in
view of the order passed by this Court dated 10th November
2021. He submitted that the rest of the directions as are
issued by this Court with regard to preparation of draft
District Survey Report (hereinafter referred to as “DSR”) and
8
consideration of the same by State Expert Appraisal
Committee (hereinafter referred to as “SEAC”) and State
Environment Impact Assessment Authority (hereinafter
referred to as “SEIAA”) are under process. He further
submitted that in view of the permission granted by this
Court vide order dated 10th November 2021, the Corporation
is employing the services of the contractor for the limited
period. He submitted that after the directions issued by this
Court are complied with, a fresh process for allotment of
sand ghats in accordance with law would be initiated subject
to the orders of this Court. He further submitted that while
permitting the mining activities through the services of the
contractor, the Corporation is ensuring that no damage is
caused to environment by such activities.
14. We had issued the directions vide order dated 10th
November 2021 in the peculiar facts and circumstances of
the matter. We had noticed that unless the detailed DSRs
are prepared by the SubDivisional Committees by
undertaking site visits and using the modern technology and
unless the same are examined by SEAC and SEIAA, it will
9
not be appropriate to carry out the mining activities.
However, we had also noticed that if there is a ban on mining
activities, apart from it leading to illegal sand mining,
criminalization and clashes between the sand mafias, it
would also cause huge loss to the public exchequer. We had
noticed that sand is also required for construction of public
infrastructural projects as well as public and private
construction activities.
15. Taking into consideration these aspects of the matter,
we had issued directions so that the SubDivisional
Committees, the SEAC and SEIAA act within the stipulated
time periods. We had granted 6 weeks’ time at each level and
had directed the matter to be kept after 20 weeks. However
noticing, that during the said period, it was necessary to
permit the mining activities so as to prevent illegal mining
and also to prevent loss to the public exchequer, we had
permitted the Corporation to carry out the mining activities,
and further to employ the services of the contractor.
However, while doing so, we had directed the State
Government to ensure that all environmental concerns are
10
taken care of and no damage is caused to the environment. It
could thus be seen that this was only a stop gap
arrangement.
16. A perusal of the NITs in question, issued by the
Corporation would reveal that the Corporation has
specifically referred to the order dated 10th November 2021,
passed by this Court and has also specified that the
operation period of sand ghats will only be up to 31st March
2022, and subject to further orders passed by this Court in
the present proceedings.
17. Insofar as the applicants in I.A. Nos. 153531153532 of
2021 and I.A. Nos.160138, 160139 and 160142 of 2021, who
claim to have a vested right in view of the extensions granted
in their favour are concerned, we see no merit in these
applications. Though they were successful in the bidding
process held in the year 2015, which was extended up to
2019 and thereafter, they were only continuing under the
extensions granted.
18. Insofar as the other applicants in I.A. Nos.154740
154741 of 2021 and I.A. No.165173 of 2021 are concerned,
11
though they were successful bidders in the tender process
conducted in the year 2019, in view of the order passed by
the Tribunal dated 14th October 2020, which was modified by
this Court vide order dated 10th November 2021, they also
cannot claim a vested right to do the mining activities.
19. Taking into consideration the peculiar facts and
circumstances in which we had passed the order, we find
that entertaining any of such applications would result in
further complications. In any case after our directions
issued on 10th November 2021 are complied with, we will
take a final look of the matter in the last week of March,
2022. The NITs issued by the Corporation for mining, cover
the period only up to 31st March 2022. We are therefore not
inclined to entertain the aforesaid four I.As.
20. Insofar as the I.A. No. 163177 of 2021, filed by the
applicant alleging contempt of this Court’s order dated 10th
November 2021 is concerned, we have already directed the
State of Bihar to ensure that while carrying out the mining
activities, it shall ensure that all environmental concerns are
taken care of and no damage is caused to the environment.
12
We remind the State Government of the said directions and
direct it to ensure that the said directions are complied with
scrupulously.
21. In that view of the matter, I.A. Nos. 154740154741 of
2021, 153531153532 of 2021, 160138 of 2021, 160139 of
2021, 160142 of 2021 and 165173 of 2021 are rejected.
22. I.A. No. 163177 of 2021 is disposed of in terms of
paragraph (20) of this order.
……....….......................J.
[L. NAGESWARA RAO]
..…....….......................J.
[B.R. GAVAI]
NEW DELHI;
JANUARY 18, 2022.
13
Landmark Cases of India / सुप्रीम कोर्ट के ऐतिहासिक फैसले
Comments
Post a Comment