CHHATTISGARH STATE POWER DISTRIBUTION COMPANY LTD. VS CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION Case
CHHATTISGARH STATE POWER DISTRIBUTION COMPANY LTD. VS CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION Supreme Court Case Judgment 2022
Landmark Cases of India / सुप्रीम कोर्ट के ऐतिहासिक फैसले
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 25782579 OF 2008
CHHATTISGARH STATE POWER DISTRIBUTION
COMPANY LTD. ...APPELLANT(S)
VERSUS
CHHATTISGARH STATE ELECTRICITY
REGULATORY COMMISSION AND ANOTHER
...RESPONDENT(S)
WITH
CIVIL APPEAL NOS. 29412942 OF 2008
CIVIL APPEAL NO. 2868 OF 2008
J U D G M E N T
B.R. GAVAI, J.
1. These appeals challenge the judgment dated 6th
December 2007 passed by the Appellate Tribunal for
Electricity (hereinafter referred to as the “APTEL”), thereby
dismissing the appeals filed by the present appellant.
2. The facts in brief giving rise to the present appeals
are as under:
1
M/s Shri Bajrang Power and Ispat Ltd. (hereinafter
referred to as “SBPIL”) has established a Captive Generation
Plant. M/s Shri Bajrang Metallics and Power Ltd. (hereinafter
referred to as “SBMPL”) is a sister concern of SBPIL. SBPIL
submitted a petition to the Chhattisgarh State Electricity
Regulatory Commission (hereinafter referred to as “the
Commission”) for providing open access and wheeling of
power through the transmission system of the appellant for
captive use by SBMPL. The petition of the SBPIL was for
permission to wheel 19 lakh units, corresponding to 13 MW,
to SBMPL. It was stated in the said petition that SBMPL
holds 27.6% of the equity shares of SBPIL and that more
than 51% of the electricity generated by the captive power
plant would be consumed by them. It was submitted that
the generating capacity of the captive generation plant set up
by SBPIL would be 103.68 MU per annum. It was further
submitted that out of the said 103.68 MU per annum power
generated, 13.22 MU per annum would be utilized in its
sponge iron plant. It was further submitted that 54 MU per
annum would be supplied to SBMPL through the appellant
grid and the balance would be sold to the appellant.
2
3. The said petition came to be resisted by the
appellant. It was contended by the appellant that SBPIL
holds more than 72% of the shares of the company.
However, its consumption would be limited only to 14.16%
(13.22 MU), whereas the consumption of SBMPL holding
26.67% shares, would be 57.87% (54 MU). It was submitted
that this was not proportionate to the ownership of the power
plant.
4. The Commission, vide its order dated 14th October
2005, rejected the contention of the appellant and held that
SBPIL was entitled to supply electricity to its sister concern
SBMPL and the same would qualify to be treated as ‘own
consumption’ within the ambit of Section 9 read with Section
2(8) of the Electricity Act, 2003 (hereinafter referred to as
“the said Act”) and Rule 3 of the Electricity Rules, 2005
(hereinafter referred to as “the said Rules”). While allowing
the said petition, the Commission imposed the following
conditions:
(i) “The consumption of electricity by the captive
users shall not be less than 51% over a
financial year, and in case it is not so it would
be treated as ‘supply of electricity by a
3
generating company’ in terms of provision of
rule 3(2) of the Rules.
(ii) The CSEB is entitled to charge for wheeling of
electricity and levy other charges as per their
present rates which shall be subject to revision
as per the provisions in regulations on the
charges for open access to be notified by the
Commission shortly.
(iii) The company may enter into necessary
agreement with the CSEB for the sale of
balance power under the present terms and
conditions of the CSEB, is subject to revision
as per the directions of the Commission from
time to time.”
5. Being aggrieved thereby, the appellant preferred
appeals before the APTEL. The said appeals came to be
dismissed by the APTEL vide impugned judgment dated 6th
December 2007. Being aggrieved thereby, the present
appeals.
6. We have heard Shri Nikhil Nayyar, learned Senior
Counsel appearing on behalf of the appellant and Shri
Naveen R. Nath, learned Senior Counsel and Smt. Swapna
Seshadari, learned counsel appearing on behalf of the
respondents.
7. Shri Nayyar submitted that the order passed by the
Commission and the impugned judgment passed by the
4
APTEL are contrary to the plain language used in Rule 3 of
the said Rules. He submitted that SBMPL is a sister concern
of SBPIL which has established the captive power plant. It is
submitted that unless SBPIL consumes 51% of the aggregate
electricity generated by it, it will not be entitled to get the
benefit under Section 9 of the said Act. He submitted that in
subrule (1) of Rule 3 of the said Rules, the words used are
“Captive Generating Plant”. He submitted that upon a plain
and literal interpretation of Rule 3 of the said Rules, it will be
abundantly clear that unless the sister concern establishes
captive generating plant utilization of 51% of the electricity
generated, it will not be entitled to get benefit under Section
9 of the said Act.
8. Shri Nath submitted that the Commission, as well as
the APTEL, has rightly construed the provisions of the said
Act and the said Rules. He submitted, that this Court, in the
case of Maharashtra State Electricity Distribution
Company Limited v. JSW Steel Limited and Others1
, has
held that no permission is required from the Commission for
supply of electricity for its own use. He further submitted
1 (2022) 2 SCC 742
5
that this Court has also held that insofar as captive users are
concerned, they are not liable to pay the additional surcharge
under Section 42(4) of the said Act.
9. Smt. Seshadari, learned counsel appearing on behalf
of the Commission submitted that if the arguments advanced
on behalf of the appellant are accepted, the same would be
contrary to the provisions of the said Act. She, therefore,
submitted that the order passed by the Commission and the
impugned judgment passed by the APTEL warrant no
interference.
10. For appreciating the rival contentions, it will be
apposite to refer to Clauses (8) and (49) of Section 2 as well
as Section 9 and subsections (1) and (2) of Section 42 of the
said Act, which read thus:
“2. Definitions.
……….
(8) “Captive generating plant” means a power plant
set up by any person to generate electricity
primarily for his own use and includes a power
plant set up by any cooperative society or
association of persons for generating electricity
primarily for use of members of such cooperative
society or association;
…………
6
(49) “person” shall include any company or body
corporate or association or body of individuals,
whether incorporated or not, or artificial juridical
person;
9. Captive generation.—(1) Notwithstanding
anything contained in this Act, a person may
construct, maintain or operate a captive generating
plant and dedicated transmission lines:
Provided that the supply of electricity from the
captive generating plant through the grid shall be
regulated in the same manner as the generating
station of a generating company:
Provided further that no licence shall be required
under this Act for supply of electricity generated
from a captive generating plan to any licensee in
accordance with the provisions of this Act and the
rules and regulations made thereunder and to any
consumer subject to the regulations made under
subsection (2) of Section 42.
(2) Every person, who has constructed a captive
generating plant and maintains and operates such
plant, shall have the right to open access for the
purposes of carrying electricity from his captive
generating plant to the destination of his use:
Provided that such open access shall be subject
to availability of adequate transmission facility and
such availability of transmission facility shall be
determined by the Central Transmission Utility or
the State Transmission Utility, as the case may be:
Provided further that any dispute regarding the
availability of transmission facility shall be
adjudicated upon by the Appropriate Commission.
42. Duties of distribution licensee and open
access.—(1) It shall be the duty of a distribution
licensee to develop and maintain an efficient, coordinated and economical distribution system in his
area of supply and to supply electricity in
7
accordance with the provisions contained in this
Act.
(2) The State Commission shall introduce open
access in such phases and subject to such
conditions, (including the cross subsidies, and other
operational constraints) as may be specified within
one year of the appointed date by it and in
specifying the extent of open access in successive
phases and in determining the charges for wheeling,
it shall have due regard to all relevant factors
including such crosssubsidies, and other
operational constraints:
Provided that such open access shall be allowed
on payment of a surcharge in addition to the
charges for wheeling as may be determined by the
State Commission:
Provided further that such surcharge shall be
utilised to meet the requirements of current level of
crosssubsidy within the area of supply of the
distribution licensee:
Provided also that such surcharge and crosssubsidies shall be progressively reduced in the
manner as may be specified by the State
Commission:
Provided also that such surcharge shall not be
leviable in case open access is provided to a person
who has established a captive generating plant for
carrying the electricity to the destination of his own
use:
Provided also that the State Commission shall,
not later than five years from the date of
commencement of the Electricity (Amendment) Act,
2003, by regulations, provide such open access to
all consumers who require a supply of electricity
where the maximum power to be made available at
any time exceeds one megawatt.
……….”
8
11. It could thus be seen that in view of Section 9 of the
said Act, any person may construct, maintain or operate a
captive generating plant and dedicated transmission lines.
The first proviso to Section 9 of the said Act provides that the
supply of electricity from the captive generating plant
through the grid shall be regulated in the same manner as
the generating station of the generating company. The
second proviso to Section 9 of the said Act provides that no
licence shall be required under the said Act for supply of
electricity generated from a captive generating plant to any
licensee in accordance with the provisions of the said Act and
the rules and regulations made thereunder and to any
consumer, subject to the regulations made under subsection (2) of Section 42 of the said Act. Subsection (2) of
Section 9 of the said Act provides that every person, who has
constructed a captive generating plant and maintains and
operates such plant, shall have the right to open access for
the purposes of carrying electricity from his captive
generating plant to the destination of his use. The first
proviso to subsection (2) of Section 9 of the said Act provides
that such open access shall be subject to availability of
9
adequate transmission facility and such availability of
transmission facility shall be determined by the Central
Transmission Utility or the State Transmission Utility, as the
case may be. The second proviso to subsection (2) of
Section 9 of the said Act provides that if there is any dispute
regarding the availability of transmission facility, it shall be
adjudicated upon by the Appropriate Commission.
12. Clause (8) of Section 2 of the said Act defines
“Captive generating plant”. It states that “Captive generating
plant” means a power plant set up by any person to generate
electricity primarily for his own use and includes a power
plant set up by any cooperative society or association of
persons for generating electricity primarily for use of
members of such cooperative society or association.
13. Clause (49) of Section 2 of the said Act defines
“person”. It states that “person” shall include any company
or body corporate or association or body of individuals,
whether incorporated or not, or artificial juridical person.
14. A combined reading of Section 9 and Clause (8) of
Section 2 of the said Act would reveal that a person is
entitled to construct, maintain or operate a captive
10
generating plant. Such a plant should be primarily for his
own use. Clause (8) of Section 2 of the said Act would
further show that it includes a power plant set up by any cooperative society or association of persons for generating
electricity. The requirement is that it should be primarily for
the use of the members of such cooperative society or
association.
15. The definition of “person” is wide enough to include
any company or body corporate or association or body of
individuals, whether incorporated or not, or artificial juridical
person.
16. It is thus clear that a person, to get benefit under
Section 9 of the said Act, could be an individual or a body
corporate or association or body of individuals, whether
incorporated or not. It could thus be seen that even an
association of corporate bodies can establish a captive power
plant. The only requirement would be that the said plant
must be established primarily for their own use. The fourth
proviso to subsection (2) of Section 42 of the said Act would
also reveal that surcharge would not be leviable in case open
access is provided to a person who has established a captive
11
generating plant for carrying the electricity to the destination
of his own use.
17. Therefore, the question that would arise is as to
whether the open access for transmitting electricity from
SBPIL to SBMPL would be for own use or not.
18. We find that Rule 3 of the said Rules would clarify
the position, which reads thus:
“3. Requirements of Captive Generating Plant.—
(1) No power plant shall qualify as a ‘captive
generating plant’ under Section 9 read with clause
(8) of Section 2 of the Act unless—
(a) in case of a power plant—
(i) not less than twentysix per cent of the
ownership is held by the captive user(s),
and
(ii) not less than fiftyone per cent of the
aggregate electricity generated in such
plant, determined on an annual basis, is
consumed for the captive use:
Provided that in case of power plant set up by
registered cooperative society, the conditions
mentioned under paragraphs at (i) and (ii)
above shall be satisfied collectively by the
members of the cooperative society:
Provided further that in case of association of
persons, the captive user(s) shall hold not less
than twentysix per cent of the ownership of
the plant in aggregate and such captive user(s)
shall consume not less than fiftyone per cent
of the electricity generated, determined on an
annual basis, in proportion to their shares in
12
ownership of the power plant within a
variation not exceeding ten per cent;
(b) in case of a generating station owned by a
company formed as special purpose vehicle for
such generating station, a unit or units of
such generating station identified for captive
use and not the entire generating station
satisfy(ies) the conditions contained in
paragraphs (i) and (ii) of subclause (a) above
including—
Explanation.—(1) The electricity required to be
consumed by captive users shall be determined with
reference to such generating unit or units in
aggregate identified for captive use and not with
reference to generating station as a whole; and
(2) The equity shares to be held by the captive
user(s) in the generating station shall not be less
than twentysix per cent of the proportionate of the
equity of the company related to the generating unit
or units identified as the captive generating plant.”
19. The provisions made in Rule 3 of the said Rules are
clear. Subrule (1) of Rule 3 of the said Rules provides that
no power plant shall qualify as a “Captive Generating Plant”
under Section 9 read with Clause (8) of Section 2 of the said
Act unless the conditions stated therein are fulfilled. The
first requirement is that not less than 26% of the ownership
is held by the captive user(s). The second requirement is
that not less than 51% of the aggregate electricity generated
in such plant, determined on an annual basis, is consumed
13
for the captive use. The second proviso to Rule 3(1)(a)(ii) of
the said Rules provides that in case of association of persons,
the captive user(s) shall hold not less than 26% of the
ownership of the plant in aggregate and such captive user(s)
shall consume not less than 51% of the electricity generated,
determined on an annual basis, in proportion to their shares
in ownership of the power plant within a variation not
exceeding 10%.
20. Admittedly, SBMPL holds 27.6% equity shares in
SBPIL. As such, the requirement of not less than 26% of
shares is fulfilled by SBMPL. As already discussed
hereinabove, even an association of corporate bodies can
establish a power plant. Since SBMPL holds 27.6% of the
ownership, the use of electricity by it would be for captive
use under the provisions of the said Act. The other
requirement would be that the consumption of SBIPL and
SBMPL together should not be less than 51% of the power
generated. Admittedly, the joint consumption by SBIPL and
SBMPL is more than 51%. As such, both the conditions as
provided under Rule 3 of the said Rules are satisfied.
14
21. We find that it will also be appropriate to refer to the
National Electricity Policy, 2005 (hereinafter referred to as
“the said Policy”) as notified by the Government of India, in
exercise of its powers under Section 3 of the said Act, on 12th
February 2005. Clauses 5.2.24 to 5.2.26 deal with the
“Captive Generation”, which read thus:
“Captive Generation
5.2.24 The liberal provision in the
Electricity Act, 2003 with respect to setting up
of captive power plant has been made with a
view to not only securing reliable, quality and
costeffective power but also to facilitate
creation of employment opportunities through
speedy and efficient growth of industry.
5.2.25 The provision relating to captive
power plants to be set up by group of consumers
is primarily aimed at enabling small and medium
industries or other consumers that may not
individually be in a position to set up plant of
optimal size in a costeffective manner. It needs
to be noted that efficient expansion of small and
medium industries across the country would
lead to creation of enormous employment
opportunities.
5.2.26 A large number of captive and
standby generating stations in India have
surplus capacity that could be supplied to the
grid continuously or during certain time periods.
15
These plants offer a sizeable and potentially
competitive capacity that could be harnessed for
meeting demand for power. Under the Act,
captive generators have access to licensees and
would get access to consumers who are allowed
open access. Grind interconnections for captive
generators shall be facilitated as per Section 30
of the Act. This should be done on priority basis to
enable captive generation to become available as
distributed generation along the grid. Towards this
end, nonconventional energy sources including cogeneration could also play a role. Appropriate
commercial arrangements would need to be
instituted between licensees and the captive
generators for harnessing of spare capacity energy
from captive power plants. The appropriate
Regulatory Commission shall exercise regulatory
oversight on such commercial arrangements
between captive generators and licensees and
determine tariffs when a licensee is the offtaker of
power from captive plant.”
[emphasis supplied]
22. It could thus be seen that the provision with respect
to establishing captive power plant has been made with a
view to not only securing reliable, quality and costeffective
power but also to facilitate creation of employment
opportunities through speedy and efficient growth of
industry. The said Policy further states that the provision
relating to captive power plants to be set up by a group of
consumers has been made primarily for enabling small and
medium industries or other consumers that may not
16
individually be in a position to set up plant of optimal size, in
a costeffective manner. It also states that the efficient
expansion of small and medium industries across the
country would lead to creation of enormous employment
opportunities. Clause 5.2.26 of the said Policy further states
that the captive and standby generating stations in India
have surplus capacity that could be supplied to the grid
continuously or during certain time periods.
23. The said Policy is issued under Section 3 of the said
Act and as such, has a statutory flavour. In any case, the
said Policy is in tune with the provisions as contained in
Section 9 and Clause (8) of Section 2 of the said Act. A
liberal provision has been made in Section 9 of the said Act
so as to promote establishment of captive power plants.
24. It is a settled position of law that the interpretation
which advances the object and purpose of the Act, has to be
preferred. A reliance in this respect can be placed on the
judgments of this Court in the cases of Administrator,
Municipal Corporation, Bilaspur v. Dattatraya
Dahankar, Advocate and Another2
, S. Gopal Reddy v.
2 (1992) 1 SCC 361
17
State of A.P.3
and Ahmedabad Municipal Corporation
and Another v. Nilaybhai R. Thakore and Another4
.
25. We are, therefore, of the considered view that no
case is made out for interfering with the order dated 14th
October 2005 passed by the Commission and the impugned
judgment dated 6th December 2007 passed by the APTEL.
26. In the result, the present appeals are found without
merit and as such, are dismissed.
27. Pending application(s), if any, shall stand disposed of
in the above terms. No order as to costs.
……..….......................J.
[L. NAGESWARA RAO]
…….........................J.
[B.R. GAVAI]
NEW DELHI;
MAY 12, 2022.
3 (1996) 4 SCC 596
4 (1999) 8 SCC 139
18
Comments
Post a Comment