National Highway Authority of India Versus Transstroy (India) Limited

National Highway Authority of India Versus Transstroy (India) Limited

Landmark Cases of India / सुप्रीम कोर्ट के ऐतिहासिक फैसले



REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6732 OF 2021
National Highway Authority of India …Appellant
Versus
Transstroy (India) Limited …Respondents
J U D G M E N T
M.R. SHAH, J.
1. Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court of Delhi in OMP No.459 of 2017 by
which the High Court has dismissed the said petition under Section 34 of
the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the
Arbitration Act, 1996”) in which the appellant – National Highway
Authority of India (hereinafter referred to as “NHAI”) prayed to set aside
the Arbitral Award dated 15.09.2017 and also the order passed by the
Arbitral Tribunal not entertaining and/or considering the counter claim
1
filed by the NHAI, the original petitioner – NHAI has preferred the
present appeal.
2. The facts leading to the present appeal and the case on behalf of
the appellant – NHAI are as under:-
2.1 That the NHAI and the respondent entered into a contract. An
Engineering Procurement and Construction (EPC) Agreement
(hereinafter referred to as “Contract”) was executed between the parties
on 13.11.2014 in respect of "improvement / augmentation of two laning
with paved shoulders from km.94/000 to km.174/000 (design chainage
from km.94/000 to km.174/000) of Karaikudi-Ramanathapuram Section
of National Highway No. 210 including 500m on SH-35 Madurai Road
(near Devakottai Rasta Railway Station) in the State of Tamil Nadu on
EPC mode (total design length 80.00kms) under NHDP PHASE-III”.
2.2 According to the NHAI, the respondent/Contractor was in
continuous breach of specific obligations under the Contract for which a
cure period notice was issued by the NHAI under Clause 23.1.1 of the
Contract as far as back on 29.09.2015 calling upon the Contractor to
cure the defaults within 60 days. The Contractor failed to cure the
defects pointed out by the NHAI, thus, a notice of intention to terminate
the Contract was issued by the NHAI on 12.04.2016 under Clause
23.1.2. The respondent/Contractor sent its reply dated 14.04.2016 to the
NHAI's notice of intention to terminate the contract. Having found the
2
reply totally unsatisfactory, the NHAI issued a termination notice dated
22.07.2016 under Clause 23.1.2 of the Contract. It is the case on behalf
of the appellant – NHAI that the NHAI specifically stated in the
termination notice that "the same is without prejudice to the Authority's
right to claim damages for the Contractor's failure to comply with the
unambiguous obligations casted upon it under the Contract and/or to
realize any dues, losses and damages whatsoever under the Contract or
under applicable laws, as the case may be".
2.3 On receipt of the termination notice, the respondent/Contractor
addressed a letter to the NHAI on 02.01.2017 to refer certain disputes
for amicable settlement under Clause 26.2 of the Contract. That
thereafter, the Contractor invoked the arbitration clause (Clause 26 of
the Contract) vide letter dated 09.02.2017 and nominated its Arbitrator
and requested the NHAI to nominate its Arbitrator so that the Presiding
Arbitrator may be appointed. The NHAI nominated its arbitrator by letter
dated 10.03.2017 which was followed by the appointment of the
Presiding Arbitrator. Accordingly, the Arbitral Tribunal came to be
constituted. The Contractor filed the Statement of Claim on 15.05.2017.
The NHAI filed its statement of defence on 11.07.2017. It is the case on
behalf of the NHAI that both in the termination notice dated 22.07.2016
as well as in the Statement of Defence dated 11.07.2017, the NHAI
3
reserved its right to claim damages and stated that it would file its
counter claim separately.
2.4 On 13.07.2017, i.e., after two days of filing the Statement of
Defence by the NHAI, the NHAI sent a letter to the Arbitral Tribunal
seeking extension of time for filing the counter claim. Vide email dated
18.07.2017 the Arbitral Tribunal rejected the NHAI's request seeking
extension of time for filing the counter claim and stated that no
application has been filed by the NHAI for filing counter claim. It appears
that thereafter the NHAI moved an application before the Arbitral
Tribunal under Section 23(2A) of the Arbitration Act to place its counter
claim on record. It appears that on the very same day, the NHAI filed its
counter claim before the Arbitral Tribunal. The Arbitral Tribunal rejected
the NHAI's application permitting it to place on record the counter claim
vide order dated 15.09.2017, essentially on the ground that the
procedure under Clauses 26.1 and 26.2 had not been followed by the
NHAI and therefore, the counter claim was beyond the scope of
arbitration agreement and adjudication of the said dispute is not within
the jurisdiction of the Arbitral Tribunal.
2.5 Feeling aggrieved and dissatisfied with the order passed by the
Arbitral Tribunal dated 15.09.2017 dismissing the application filed by the
NHAI seeking permission to place on record the counter claim and
holding that the dispute raised by the NHAI in the counter claim is not
4
within the scope of arbitration agreement and that the dispute sought to
be filed is contractually not arbitrable and the adjudication of the said
dispute is not within the jurisdiction of the Arbitral Tribunal, NHAI
preferred the appeal under Section 34 of the Arbitration Act, 1996 before
the High Court of Delhi.
2.6 Before the High Court, an objection was raised on behalf of the
Contractor on maintainability of the application under Section 34 of the
Arbitration Act, 1996. However, treating the order dated 15.09.2017
passed under Section 16(2) of the Arbitration Act, 1996, the High Court
has treated the proceedings before it as one under Section 37(2) of the
Arbitration Act, 1996 while deciding on the admissibility of the counter
claim and thereafter has decided the same on merits.
2.7 By the impugned judgment and order, the High Court has
dismissed the said application and has confirmed the order passed by
the Arbitral Tribunal dated 15.09.2017 rejecting the application submitted
by NHAI to take the counter claim on record.
2.8 Feeling aggrieved and dissatisfied with the impugned judgment
and order passed by the High Court, the NHAI has preferred the present
appeal.
3. Ms. Madhavi Diwan, learned ASG has appeared on behalf of the
NHAI and Shri Nakul Dewan, learned Senior Advocate has appeared on
behalf of the respondent – Contractor.
5
4. Ms. Madhavi Diwan, learned ASG appearing on behalf of the NHAI
has vehemently submitted that in the facts and circumstances of the
case, the High Court has committed a grave/serious error in confirming
the order passed by the Arbitral Tribunal not taking on record the counter
claim filed by the NHAI.
4.1 it is further submitted by Ms. Diwan, learned ASG that, both, the
Arbitral Tribunal as well as the High Court have failed to appreciate that
the counter claim was based on common/overlapping cause of action. It
is submitted that the arbitration invoked by the Contractor arose out of
the very termination notice which had been issued by the NHAI.
Therefore, the foundation of the Contractor’s case before the Arbitral
Tribunal is the validity of such termination. Therefore, there was no
question of seeking to hair split the dispute between the parties. It would
lead to unnecessary multiplicity of proceedings and needless cost and
inconvenience when the evidence itself is also common because the
dispute arises out of the same transaction.
4.2 It is further submitted by Ms. Diwan, learned ASG that as such
Clause 26 can be invoked by either party. It is submitted that Clause 26
of the Contract is self-explanatory, where it refers to 'any dispute',
difference or controversy being required to be attempted to be amicably
resolved in accordance with the conciliation procedure under Clause
26.2. It is submitted that the provision requires the same to be notified in
6
writing by either party. Likewise, Clause 26.2 states that either party may
call upon the Authority's Engineer or such other person as the parties
may mutually agree upon to mediate and arrive at an amicable
settlement. It is submitted that the reason and the rationale behind
permitting either party to invoke Clause 26.1 is that by its very definition
'a dispute' is two sided. On interpretation of the word ‘dispute’, reliance is
placed upon the decisions of this Court in the case of Gujarat State
Cooperative Land Development Bank Ltd. Vs. P.R. Mankad and
Ors., (1979) 3 SCC 123 (para22) and Major (Retd.) Inder Singh Rekhi
VS. Delhi Development Authority, (1988) 2 SCC 338 (para 4).
4.3 Relying upon the aforesaid two decisions, it is further submitted by
Ms. Madhavi Diwan, learned ASG that in the present case, the word
"Dispute" has been used by the Contractor itself in its notice dated
02.01.2017 as well as in his letter dated 09.02.2017 whereby the
Contractor itself had referred the Termination Notice as an unilateral
decision from which a "Dispute" has arisen. It is submitted that thus, the
Dispute in the present case is with regard to the termination notice dated
22.07.2016 issued by the NHAI. It is submitted that therefore, it would
be a travesty of process to interpret "Dispute" as only allowing for the
claim made on behalf of the Contractor to be submitted to the process
contemplated under Clause 26. It is submitted that the Arbitral Tribunal
and the High Court have failed to appreciate the difference between the
7
expressions 'claim' which may be made by one side and 'Dispute' which
by its definition has two sides. It is submitted that the language of
Clause 26 itself contemplates that "either party" to the dispute may
invoke this procedure. It is submitted that therefore there can be no
question of duplication of very same process which has been invoked
beforehand and eventually culminated in arbitration process. It is
submitted that the second round under Clause 26 would in any event be
an exercise in futility in as much as very same issue would have been
brought up namely whether termination of contract was lawful or not,
which issue by then was already pending before the Arbitral Tribunal.
4.4 It is further submitted that the Arbitral Tribunal as well as the High
Court have failed to appreciate that it was the NHAI who was compelled
to terminate the contract after providing sufficient opportunities to the
Contractor to cure the defects. The NHAI specifically reserved its right in
the termination notice itself to claim damages which is a natural
consequence of termination for Contractor's failure to comply with its
obligations. It is submitted that therefore the contention on behalf of the
Contractor that the counter claim was by surprise or by way of
counterblast be stated to be rejected.
4.5 It is submitted that even it cannot be said that NHAI by submitting
the counter claim has bypassed the procedure which the parties had
agreed. It is submitted that there can be no question of bypassing the
8
procedure when that stage has already passed in the present case. It is
submitted that Clause 26 does not contemplate repeated invocation of
same procedure when there is an overlapping cause of action and the
repetition of process would be completely meaningless.
4.6 It is submitted that as per the settled position of law, rules or
procedures are the handmaids and not the mistress of justice. The
procedural provisions cannot be interpreted in a hyper-technical manner
to waste the time and resources of parties contrary to the letter and spirit
of the Arbitration Act.
4.7 It is vehemently submitted by Ms. Diwan, learned ASG that in the
present case not taking on record the counter claim filed by the NHAI,
the Arbitral Tribunal and the High Court both have lost sight of the very
object and purpose of Section 23(2A) which is meant to provide
convenience to the parties in being able to file the entirety of their
claim/counter claim, etc. before the Arbitral Tribunal. It is submitted that
therefore, there was absolutely no reason for the High Court to have
excluded the counter claim which was sought to be filed before the
Arbitral Tribunal by the NHAI within two days of filing of its Statement of
Defense. It is submitted that Section 23 has been amended pursuant to
the recommendation of the Law Commission of India in its Report No.
246 "to ensure that counter claims and set off can be adjudicated upon
by an arbitrator without seeking a separate/new reference by the
9
respondent so long as it falls within the scope of the arbitration
agreement, in order to ensure final settlement of disputes between
parties and prevent multiplicity of litigation".
4.8 Making above submissions and relying upon the decisions of this
Court in the case of State of Goa Vs. Praveen Enterprises, (2012) 12
SCC 581; Bharat Petroleum Corporation Limited Vs. Go Airlines
(India) Limited, (2019) 10 SCC 250; Silpi Industries Etc. Vs. Kerala
State Road Transport Corporation and Anr., 2021 SCC Online SC
439 and the decision of the Calcutta High Court in the case of Kolkata
Metropolitan Development Authority Vs. Hindustan Construction
Co. Ltd., 2017 SCC OnLine Cal 18978 (against which Special Leave
Petition (C) Nos. 18443-18444 of 2018 were filed and the same were
dismissed by this Court by order dated 23.07.2018), it is prayed to allow
the present appeal and to direct the Arbitral Tribunal to take on record
the counter claim filed by the NHAI and adjudicate the same in
accordance with law.
5. Present appeal is vehemently opposed by Shri Nakul Dewan,
learned Senior Advocate appearing on behalf of the respondent –
Contractor.
5.1 Shri Nakul Dewan, learned Senior Advocate appearing on behalf
of the respondent – Contractor has made following broad submissions in
10
support of his prayer to dismiss the present appeal. He has submitted
as under:-
(i) Clause 26 of the EPC Contract mandatorily required the
parties to attempt to amicably settle the Disputes (identified
and crystallised prior to the reference) as a pre-condition to
the invocation of arbitration. That has not been done by the
appellant – NHAI with respect to its counter claim.
(ii) The term "Disputes" defined and set out in Clause 26.1.1.
has to be strictly construed to mean those disputes which
were identified by any party and referred for conciliation
under Clause 26.1.1 read with Clause 26.2. No such
identification had been done by the appellant - NHAI for its
counter claim, meaning thereby that they cannot be raised by
the appellant - NHAI.
(iii) The mere reservation of rights would not entitle either party
to bypass the contractually agreed mechanism under Clause
26 of the EPC Contract.
(iv) Section 23(2A) of the Act does not permit a counter claim to
be raised in a manner which is inconsistent with the
agreement of the parties.
5.2 Elaborating above submissions, it is submitted by Shri Nakul
Dewan, learned Senior Advocate appearing on behalf of the respondent
– Contractor that Clause 26 of the EPC Contract is clear and
unambiguous. It lays down a two-step process prior to the invocation of
11
the arbitration process. It is submitted that the EPC Contract does not
contemplate parties directly raising claims by directly resorting to
arbitration without going through the steps set out in Clause 26. It is
submitted that Step 1 can be said to be “Notification of Disputes”. In the
event that a "dispute, difference, or controversy" has arisen between the
parties, then it has to be "notified in writing' to the other party. This
notification can be done by any party which has a dispute. Such
notification then gives rise to a "Dispute" defined and contemplated
under Clause 26.1.1 of the EPC Contract
5.3 It is submitted that Step 2 is with respect to “Resolution by
amicable settlement”. Under the Step 2, the parties are then required to
attempt to amicably resolve the “Dispute” in accordance with the
conciliation procedure set out at Clause 26.2. The mandatory
requirement of conciliation is evident by the use of the word "shall" in
Clause 26.1.1. It is submitted that as per Clause 26.2, the dispute is
required to be mediated by NHAI's Engineer or such other person as
mutually decided, which is called the Conciliator under the EPC
Contract. Failing such mediation or without the intervention of the
Conciliator, either party may refer the dispute to NHAI's Chairman for
amicable settlement, following the time-bound procedure set out in
Clause 26.2.
12
5.4 It is submitted that Step 3 is “Invocation of arbitration”. It is
submitted that it is only on the failure to resolve the dispute amicably that
the Dispute notified under Clause 26.1.1. is thereafter referred to
arbitration. Clause 26.3.1 clearly lays down that any "Dispute, which is
not resolved amicably as provided under Clause 26.1 and Clause 26.2"
shall be finally referred to arbitration. It is submitted that therefore only
those Disputes which are not resolved after Steps 1, 2 and 3 alone, can
be the subject matter of dispute before the Arbitral Tribunal.
5.5 It is submitted that any interpretation permitting the parties to
bypass the mechanism laid down in the EPC Contract, unless waived,
would amount to a rewriting of the contract. It is submitted that as
observed and held by this Hon’ble Court in the case of M.K. Shah
Engineers & Contractors Vs. State of MP. (1999) 2 SCC 594, a prearbitral requirement is an essential facet of the arbitration clause.
Reliance is also placed on the decision of the Kerala High Court in the
case of Nirman Sindia v. Indal Electromelts Ltd., Coimbatore 1999
SCC OnLine Ker 149. It is submitted that in the aforesaid decision, the
Hon’ble High Court of Kerala has held that "when the parties to a
contract agree to any special mode for resolution of the disputes arising
out of the agreement and they are bound to comply with the mode
prescribed under the agreement. Without resorting to the first step
provided for the resolution of the dispute in the agreement they cannot
13
jump to the second step or to the final step to settle the disputes
between the parties".
5.6 It is further submitted by Shri Nakul Dewan, learned Senior
Advocate appearing on behalf of the respondent – Contractor that the
mandatory and enforceable nature of contractually stipulated preconditions to arbitration, which are aimed at dispute resolution through
mediation or negotiations, have also been held to be enforceable
internationally.
5.7 It is submitted that therefore as Clause 26 of the EPC Contract is
mandatory in nature, no claim should be allowed to be introduced in a
manner contrary to the contractual mechanism may be by way of
counter claim.
5.8 It is further submitted by Shri Nakul Dewan, learned Senior
Advocate appearing on behalf of the respondent – Contractor that in the
present case the parties have contractually defined and limited the term
“Dispute” at Clause 26.1.1 of the EPC Contract to mean any dispute,
difference, or controversy "notified in writing by either Party to the other
Party". It is submitted that Clause 1.1 of the EPC Contract further sets
out that "words and expressions beginning with capital letters and
defined in this Agreement ... shall, unless the context otherwise requires,
have the meaning ascribed thereto herein ...
14
5.9 It is submitted that therefore having contractually agreed to only
define notified disputes as “Disputes” and further restricting the
reference of only such “Disputes” to arbitration under Clause 26.3 as
only those which are notified by parties under Clause 26.1 and referred
to conciliation under Clause 26.2, no other interpretation, contrary to the
written contract should be taken. That is because Courts give effect to
the contractual bargain of the parties unless such bargain is contrary to
statute or against public policy, neither of which exception has or can be
pleaded in this case.
5.10 It is submitted that the submission on behalf of the NHAI that the
counter claims arise out of the unlawful termination of the EPC Contract,
and that it falls within the definition of “Dispute” and that the term
“Dispute” ought to be widely construed to include the counter claims that
may arise out of the termination of the EPC Contract is to be rejected
outright. It is submitted that the use of the words "any Dispute" used in
Clause 26.3.1 also ought to be accordingly construed to mean only
those matters which have been notified by the parties for amicable
settlement under Clause 26.1.
5.11 Now, so far as the assertion on behalf of the appellant – NHAI that
having reserved its rights to raise counter claim at the stage of
termination as well as of filing its Statement of Defence, it is entitled to
raise the counter claim and the submission that permitting the NHAI to
15
file the counter claim would avoid multiplicity, it is submitted that the said
assertion is without any basis. It is submitted that the mandatory nature
of Clause 26 which required a party to crystallise and notify its Dispute to
the other party is a clause which seeks to ensure that only those claims
that are notified get adjudicated.
5.12 It is submitted that if the NHAI had any genuine claim, then it ought
to have notified the respondent - Contractor in accordance with Clause
26.1.1 of the EPC Contract. The NHAI could have done so even after the
Contractor sought to refer the Disputes to arbitration where it ought to
have sought the adjudication of its counter claims. However, it did not
do so and instead, expressly sought to refer the "disputes under
reference raised by the contractor". Thus, waiving its rights to refer any
counter claims to arbitration. It is submitted that that being the case, the
NHAI should not be allowed to introduce a counter claim of INR 208
crores through a circuitous interpretation of Section 23(2A) of the Act.
5.13 Now, so far as reliance placed upon Section 23(2A) of the Act
relied upon on behalf of the NHAI, it is submitted that though Section
23(2A) of the Act recognises the right of a respondent to raise counter
claims, the language of the statute is clear. In terms of Section 23(2A),
the Tribunal has jurisdiction over such counter claims, "if such counter
claim or set-off falls within the scope of the arbitration agreement."
16
5.13.1 It is submitted that in a given case the scope of the
arbitration agreement, as set out under Section 23(2A) of the Act, must
be ascertained by a conjoint reading of Sections 2(1)(b), 7 and 21 of the
Act read along with the arbitration clause. It is submitted that on a
conjoint reading of the aforesaid provisions of the Arbitration Act, 1996, it
is apparent that parties are fully entitled to choose which disputes get
referred to arbitration. The same is consistent with the recognition of the
party autonomy. It is submitted that in the present case, the parties have
chosen through the mechanism set out under Clause 26.1.1 read with
Clause 26.3.1 that only those disputes notified by one party to the other
and first categorised under the head of a Dispute which cannot be
"resolved amicably" under Clause 26.2 can be referred to arbitration. It
is submitted that therefore a counter claim directly brought before the
Tribunal without having been categorised as a “Dispute” in terms of
Clause 26.1 and that too by bypassing the mandatory pre-conditions
agreed between the parties would fall outside the scope of the arbitration
agreement as specified under Section 23(2A) and hence beyond the
jurisdiction of the Tribunal.
5.14 Making above submissions, it is vehemently submitted that in the
present case, both the Arbitral Tribunal as well as the Hon’ble High Court
have not committed any error in not permitting the NHAI to file the
counter claim, which was filed straightaway before the Arbitral Tribunal
17
without following the procedure as required under Clause 26. Therefore,
it is prayed to dismiss the present appeal.
6. We have heard the learned counsel for the respective parties at
length.
7. The short question, which is posed for the consideration of this
Court is :
Whether in the facts and circumstances of the case, the High
Court as well as the Arbitral Tribunal have committed any error in
rejecting the application submitted by NHAI under Section 23(2A)
of the Arbitration Act, 1996 not permitting the NHAI to take on
record the counter claim?
8. At the outset, it is required to be noted that in the present case, the
NHAI submitted the Statement of Defence on 11.07.2017 in which the
NHAI reserved its right to claim damages and stated that it would file its
counter claim separately and after two days only, i.e., on 13.07.2017,
sent a letter to the Arbitral Tribunal seeking extension of time for filing the
counter claim, which came to be rejected by the Arbitral Tribunal vide
e-mail on 18.07.2017. That thereafter, immediately the NHAI moved an
application before the Arbitral Tribunal under Section 23(2A) of the
Arbitration Act, 1996 to place its counter claim on record. In this factual
background, the aforesaid issue/question posed for consideration of this
Court is required to be considered.
18
9. While answering the aforesaid question, the relevant clauses of
the Contract between the parties and the relevant provisions of the
Arbitration Act, 1996 are required to be referred to.
10. Clause 26 of the Contract is with respect to the dispute resolution.
Clause 26.1 to Clause 26.3.1, which are relevant for our purpose are as
under:-
“26.1 Dispute Resolution
26.1.1 Any dispute, difference or controversy of whatever
nature howsoever arising under or out of or in relation
to this Agreement (including its interpretation) between
the Parties, and so notified in writing by either Party to
the other Party (the "Dispute") shall, in the first
instance, be attempted to be resolved amicably in
accordance with the conciliation procedure set forth in
Clause 26.2.
26.1.2 The Parties agree to use their best efforts for
resolving all Disputes arising under or in respect of this
Agreement promptly, equitably and in good faith, and
further agree to provide each other with reasonable
access during normal business hours to all nonprivileged records, information and data pertaining to
any Dispute.
26.2 Conciliation
In the event of any Dispute between the Parties, either
Party may call upon the Authority's Engineer, or such
other person as the Parties may mutually agree upon
(the "Conciliator") to mediate and assist the Parties in
arriving at an amicable settlement thereof. Failing
mediation by the Conciliator or without the intervention
of the Conciliator, either Party may require such
19
Dispute to be referred to the Chairman of the Authority
and the Chairman of the Board of Directors of the
Contractor for amicable settlement, and upon such
reference, the said persons shall meet no later than 7
(seven) business days from the date of reference to
discuss and attempt to amicably resolve the Dispute. If
such meeting does not take place within the 7 (seven)
business day period or the Dispute is not amicably
settled within 15 (fifteen) days of the meeting or the
Dispute is not resolved as evidenced by the signing of
written terms of settlement within 30 (thirty) days of the
notice in writing referred to in Clause 26.1.1 or such
longer period as may be mutually agreed by the
Parties, either Party may refer the Dispute to
arbitration in accordance with the provisions of Clause
26.3.
26.3 Arbitration
26.3. "Any Dispute, which is not resolved amicably as
provided in clause 26.1 & 26.2 shall be finally settled
by arbitration as set forth below:
i) The Dispute shall be finally settled by arbitration in
accordance with the Arbitration & Conciliation Act,
1996, or any statutory amendment thereof. The Arbitral
tribunal shall consist of 3 Arbitrators, one each to be
appointed by NHAI and the Contractor. The third
Arbitrator shall be chosen by the two Arbitrators so
appointed by the Parties and shall act as Presiding
Arbitrator. In case of failure of the two Arbitrators,
appointed by the parties to reach upon a consensus
within period of 30 days from the appointment of the
Arbitrator appointed subsequently, the Presiding
Arbitrator shall be appointed by the Chairman of the
Executive Committee of the Indian Roads Congress.
ii) Neither party shall be limited in the proceedings before
such Tribunal to the evidence or arguments before the
other party /Independent consultant.
20
iii) Arbitration may be commenced during or after the
Contract Period, provided that the obligations of NHAI
and the Contractor shall not be altered by reason of
the arbitration being conducted during the Contract
Period.
iv) If one of the parties fails to appoint its Arbitrator in
pursuance of Sub-Clause (1) above, within 30 days
after receipt of the notice of the appointment of its
Arbitrator by the other party, then the Chairman of the
Executive Committee of the Indian Roads Congress,
shall appoint the Arbitrator. A certified copy of the order
of the Chairman of the Executive Committee of the
Indian Roads Congress making such an appointment
shall be furnished to each of the parties.
v) Arbitration proceedings shall be held at Delhi, India,
and the language of the Arbitration Proceedings and
that of all documents and communications between the
parties shall be English.
xxxxxxxxxxxxxx”
11. Section 23 of the Arbitration Act, 1996 as amended by Act No. 3 of
2016 is as under:-
“23. Statements of claim and defence.—(1) Within the
period of time agreed upon by the parties or determined by
the arbitral tribunal, the claimant shall state the facts
supporting his claim, the points at issue and the relief or
remedy sought, and the respondent shall state his defence
in respect of these particulars, unless the parties have
otherwise agreed as to the required elements of those
statements.
(2) The parties may submit with their statements all
documents they consider to be relevant or may add a
reference to the documents or other evidence they will
submit.
21
(2A) The respondent, in support of his case, may also
submit a counter-claim or plead a set-off, which shall be
adjudicated upon by the arbitral tribunal, if such counterclaim or set-off falls within the scope of the arbitration
agreement.
(3) Unless otherwise agreed by the parties, either party
may amend or supplement his claim or defence during the
course of the arbitral proceedings, unless the arbitral tribunal
considers it inappropriate to allow the amendment or
supplement having regard to the delay in making it.
(4) The statement of claim and defence under this
section shall be completed within a period of six months from
the date the arbitrator or all the arbitrators, as the case may
be, received notice, in writing of their appointment.”
12. Thus, from the aforesaid, it may be seen that Clause 26 – Dispute
Resolution Clause, i.e., Clause 26.1 and Clause 26.2, are in the nature
of conciliation. Both the parties are given opportunity to resolve the
dispute amicably and efforts are to be made through conciliation to
resolve the “Dispute” and thereafter the “Dispute”, which is not resolved
amicably, shall have to be finally settled by the arbitration. The words
used are “any dispute, difference or controversy of whatever nature
howsoever arising under or out of or in relation to this agreement
between the parties……..”. It is required to be noted that in the present
case, the cause for the dispute between the parties was the termination
of the contract by the NHAI. As far as the said dispute of termination of
notice was required to be resolved amicably as per the procedure
prescribed under Clauses 26.1 and 26.2 of the Contract Agreement. It
may be true that in a given case, the “Dispute” may include the claims
22
and/or counter claims, but, at the same time, the main dispute can be
said to be termination of the contract, which as observed hereinabove
was required to be resolved through conciliation after following the
procedure as above. In the present case, the communication dated
02.01.2017 addressed by the Contractor to the Chairman, NHAI, it was
stated as under:-
“Due to this unilateral action of the Authority a Dispute has
arisen between the parties to the agreement. As the dispute
has already arisen, it is required the dispute to be referred to
the Chairman of the Authority in accordance with the Clause
26.2 of the Contract Agreement for an amicable settlement.”
12.1 Even in the notice invoking arbitration dated 09.02.2017, it is
stated as under:-
“However the Authority has terminated the Contract
Agreement and invoked the performance Bank Guarantee of
Rs.21.00 Cr.
Due to this unilateral and illegal action of the Authority by a
Dispute has arisen between the parties to the agreement.
In accordance with the Clause 26.3.1 of the Contract
Agreement "Any dispute which is not resolved amicably as
provided in Clause 26.1 & 26.2 shall be finally settled by
arbitration as set forth below”
i) The Dispute shall be finally settled by arbitration in
accordance with the Arbitration & Conciliation Act,
1996, or any statutory amendment thereof. The Arbitral
tribunal shall consist of 3 Arbitrators, one each to be
appointed by NHAI and the Contractor. The third
Arbitrator shall be chosen by the two Arbitrators so
appointed by the Parties and shall act as Presiding
Arbitrator.
ii) Accordingly we are nominating Shri D Sree Rama
Murthy, as our arbitrator, whose consent is enclosed
23
herewith. We humbly request you to nominate your
arbitrator so that the third arbitrator shall be appointed
by the two arbitrators so appointed by the Parties and
shall act as Presiding Arbitrator.”
13. Therefore, thereafter, it is not open for the Contractor to contend
that the counter claim was without following the procedure as required in
Clauses 26.1 and 26.2 and, therefore, may not be taken on record. On
a true and fair interpretation of Clause 26, failure to resolve the dispute
(in the present case, the termination of the Contract by the NHAI), the
arbitration proceedings would be maintainable. That does not mean that
only a claim and/or counter claim as sought to be contended on behalf of
the Contractor now would alone be entertained.
13.1 Both the Arbitral Tribunal as well as the High Court have failed to
appreciate the difference between the expressions “claim”, which may
be made by one side and “Dispute”, which by its definition has two sides.
13.2 At this stage, it is required to be noted that even the Arbitral
Tribunal while rejecting the application of the NHAI for extension of time
to file the counter claim did not observe and/or rejected the application
for extension of time to file the counter claim on the ground that the said
counter claim would not be maintainable without following the process as
required under Clause 26 of the Contract agreement. The order dated
18.07.2017 passed by the Arbitral Tribunal rejecting the application
24
submitted by NHAI for extension of time to file the counter claim is as
under:-
“This has reference to the respondent’s letter dated July 13,
2017 making request for extending the lime by 4 weeks for
filing of the counterclaims. In this connection the AT has to
remind the respondent that at the time of first and
preliminary meeting held on 20.04.2017, while fixing the
schedule for filing of pleadings by the parties, the AT had
specifically brought the fact to the notice of both the parties
including the respondent, vide para 12.0 of the minutes of
the said meeting, that the present arbitral matter is covered
under the Act of 1996 as amended in year 2015 and
therefore the adjudication is to be completed within one year
and therefore the directions given by the AT shall be
complied with within the time frame indicated without being
required to seek any postponement or extension of time.
Further the last date for filing of the SOD was determined in
consultation with the respondent to be on or before
30.06.2017. The SOD was however filed by the respondent
on 11.07.2017 after seeking an extension of time for 2
weeks. The AT had granted the said extension with a view to
give the respondent a reasonable opportunity to present its
case. Now the respondent is seeking an extension of time
for filing of the counterclaims.
It may be mentioned here that the claimant has, vide its
email dated 18.07.2017, objected to grant of any extension
of time for filing of the counterclaims for the reasons stated
therein,
The AT has given thought to request made by the
respondent taking into consideration the procedure and
schedule of filing of pleadings agreed upon by both the
parties as detailed in the Proceedings of the AT dated
20.04.2017 and the Act of 1996 as amended in year 2015.
The AT observes that sub-sections 23(2) and 23(2A) of the
amended Act of 1996, read together provide that the
respondent may, in support of his case, also submit a
counterclaim or plead a set-off, along with its Statement of
Defence for adjudication by the AT. The AT observes that the
respondent has pleaded a set-off of Rs. 1.23 crores vide its
25
Statement of Defence; while as regards the counterclaims, it
has been stated therein that the respondent reserves its right
to file the counterclaims. The respondent has not stated any
applicable law in respect of reserving such right.
In the above background, the AT observes that (i) during the
proceedings the procedure and schedule for filing the
pleadings were determined by the AT as agreed to by both
the parties; that there is no mention therein for filing of the
counterclaims by the respondent and (ii) the Statement of
Defence has already been filed by the respondent, with setoff and without any counterclaim as per the procedure
agreed to by and between the parties, except that the
respondent has sue moto reserved its right to file
counterclaim at a later date. Thereafter there is no
application by the respondent for filing of any counterclaim.
In the above circumstances, there is no question of having
any date determined by the AT or agreed upon by the parties
for filing the counterclaim by the respondent, and if there is
no date fixed or agreed upon for filing of the counterclaims,
the question of its extension does not arise. Therefore, the
AT orders that the request for an extension of time for filing
of the counterclaim made by the respondent is not in
accordance with applicable law and is irrelevant in view of
the factual circumstances as above.
In view of the delay in filing of the SOD by the respondent,
the claimant shall file its rejoinder thereon, if any, on or
before 05.08.2017 and the statement of admission and
denial of documents shall be filed by the parties on or before
11.08.2017i.e. the date of the next meeting of the AT.
The above decision of the AT does not preclude the
respondent from having another legal remedy in respect of
its claims.
The above Order is issued by the Presiding Arbitrator in
consultation with and on behalf of the AT.”
13.3 However, thereafter, when the NHAI filed the application under
sub-section (2A) of Section 23 of the Arbitration Act, 1996 seeking to
26
place on record its counter claim, by order dated 15.09.2017, the Arbitral
Tribunal rejected the said application by observing that in the application
for permitting the NHAI to place on record the counter claim, the NHAI
has not stated anything about having made an attempt for such
amicable settlement. However, it is required to be noted that from the
very beginning, the NHAI reserved its right to claim the damages and
even in the Statement of Defence also claimed such a set off of Rs.1.23
crores and also specifically stated therein that the NHAI reserved its right
to file the counter claim. Therefore, on the grounds on which the Arbitral
Tribunal had rejected the application of NHAI to place on record the
counter claim can be said to be contrary to the intent between the parties
to resolve the dispute (which was for termination of the Contract by the
NHAI) through conciliation first. In the facts and circumstances of the
case, by such a narrow interpretation, the Arbitral Tribunal has taken
away the valuable right of the NHAI to submit counter claim, which is of
a very huge amount thereby negotiating the statutory and contractual
rights of the NHAI and paving way for a piecemeal and inchoate
adjudication.
13.4 When there is a provision for filing the counter claim – set off,
which is expressly inserted in Section 23 of the Arbitration Act, 1996,
there is no reason for curtailing the right of the appellant for making the
counter claim or set off. If we do not allow the counter claim made by
27
the NHAI in the proceedings arising out of the claims made by the
Contractor, it may lead to parallel proceedings before various fora.
While passing the impugned judgment and order, the High Court has lost
sight of the aforesaid aspect, which ought to have been considered while
considering the request on behalf of the NHAI to place on record its
counter claim. Clauses 26.1 and 26.2 have to be interpreted in a
pragmatic and practical manner, as they require that the parties must at
first try to settle, resolve and even try conciliation but when the
procedure under Clauses 26.1 and 26.2 fails to yield desired result, in
the form of settlement within the period specified in Clause 26.2, the
Dispute can be resolved through arbitration in terms of Clause 26.3.
Once any dispute, difference or controversy is notified under Clause
26.1, the entire subject matter including counter claim/set off would form
subject matter of arbitration as “any dispute which is not resolved in
Clauses 26.1 and 26.2”.
13.5 At this stage, it is required to be noted that as such there was no
delay at all on the part of the NHAI initially praying for extension of time
to file the counter claim and/or thereafter to file application under Section
23(2A) permitting it to place on record the counter claim. In the facts
and circumstances of the case, we are of the opinion that not permitting
the NHAI to file the counter claim would defeat the object and purpose of
permitting to file the counter claim/set off as provided under Section
28
23(2A) of the Arbitration Act, 1996. Without appreciating the aforesaid
aspects, the High Court has by the impugned judgment and order, and
on narrow interpretation of Clause 26 has seriously erred in rejecting the
application under Section 34/37 of the Arbitration Act, 1996 and
confirming the order passed by the Arbitral Tribunal in not permitting the
NHAI to file the counter claim. The High Court ought to have
appreciated that permitting the NHAI to file the counter claim may avoid
multiplicity of proceedings.
14. In view of the above and for the reasons stated above, the order
passed by the Arbitral Tribunal dated 15.09.2017 and the impugned
judgment and order passed by the High Court deserve to be quashed
and set aside and are accordingly quashed and set aside.
Consequently, the application submitted by NHAI to permit it to file the
counter claim is hereby allowed and the NHAI is permitted to file the
counter claim, which the Arbitral Tribunal to consider alongwith the
Statement of Claim submitted by the Contractor and the Statement of
Defence of claim submitted by the NHAI on its own merits. In view of the
delay occasioned by the impugned orders, we direct that the period
between 18.07.2017 till 11.07.2022 shall be excluded for computing the
period for passing of the award under Section 29A of the Arbitration Act,
1996.
29
Present Appeal is accordingly Allowed. However, in the facts and
circumstances of the case, there shall be no order as to costs.
Pending applications, if any also stand disposed of.
…………………………………..J.
[M.R. SHAH]
NEW DELHI; …………………………………..J.
JULY 11, 2022. [SANJIV KHANNA]
30

Comments

Popular posts from this blog

100 Questions on Indian Constitution for UPSC 2020 Pre Exam

भारतीय संविधान से संबंधित 100 महत्वपूर्ण प्रश्न उतर

संविधान की प्रमुख विशेषताओं का उल्लेख | Characteristics of the Constitution of India