Indian Oil Corporation Limited Versus NCC Limited
Indian Oil Corporation Limited Versus NCC Limited
Landmark Cases of India / सुप्रीम कोर्ट के ऐतिहासिक फैसले
// 1 //
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 341 OF 2022
(@ SLP (C) No.13161/2019)
Indian Oil Corporation Limited …Appellant(s)
Versus
NCC Limited …Respondent(s)
With
CIVIL APPEAL NO. 342 OF 2022
(@ SLP (C) No.13408/2019)
CIVIL APPEAL NO. 344 OF 2022
(@ SLP (C) No.13815/2019)
CIVIL APPEAL NO. 343 OF 2022
(@ SLP (C) No.13813/2019)
CIVIL APPEAL NO. 345 OF 2022
(@ SLP (C) No.13816/2019)
J U D G M E N T
M.R. SHAH, J.
1. As common questions of law and facts arise in this
group of appeals and as such between the same parties
and with respect to similar contracts / agreements, all
these appeals are decided and disposed of together by
this common judgment and order.
// 2 //
2. Feeling aggrieved and dissatisfied with the impugned
judgment and orders passed by the High Court of Delhi,
New Delhi in respect to Arbitration Petitions by which,
in exercise of powers under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (hereinafter
referred to as “Arbitration Act”), the High Court has
allowed the said petitions and has appointed the learned
Arbitrator by referring the dispute between the parties
for arbitration, the Indian Oil Corporation Limited has
preferred the present appeals.
3. For the sake of convenience, Civil Appeal arising out of
Special Leave Petition No.13161/2019 arising out of the
order passed by the High Court in Arbitration Petition
No.115/2018 is treated as the lead matter.
4. The facts leading to the present appeal in a nutshell are
as under:
4.1. That, the appellant, Indian Oil Corporation Limited
(hereinafter referred to as “IOCL”) floated a tender
in respect of the works described as “Civil,
Structural & Associated UG piping works of VGOHDT, DHDT & HCDS Units (EPCM2) for Paradip
Refinery Project”. The respondent herein – NCC
Ltd. (hereinafter referred to as “NCCL”) was
declared the successful bidder. After issuance of
the Letter of Acceptance dated 17.03.2010, a
// 3 //
formal agreement was executed between the
parties dated 28.04.2010. The relevant clauses of
the Agreement which may have a bearing on the
issues involved in the present appeals are as
under:
“1.21.0.0 “Notified Claim” shall mean a claim of the
CONTRACTOR notified in accordance with the
provisions of Clause 6.6.1.0 hereof.
xxx xxx xxx
CLAIMS BY THE CONTRACTOR
6.6.1.0 Should the CONTRACTOR consider that he is
entitled to any extra payment or compensation
in respect of the works over and above the
amounts due in terms of the Contract as
specified in Clause 6.3.1.0 hereof or should
the CONTRACTOR dispute the validity of any
deductions made or threatened by the OWNER
from any Running Account Bills, the
CONTRACTOR shall forthwith give notice in
writing of his claim in this behalf to the
EngineerinCharge and the Site Engineer
within 10 (ten) days from the date of the issue
of orders or instructions relative to any works
for which the CONTRACTOR claims such
additional payment or compensation or of the
happening of other event upon which the
CONTRACTOR bases such claim, and such
notice shall give full particulars of the nature
of such claim, grounds on which it is based,
and the amount claimed. The OWNER shall
not anywise be liable in respect of any claim
by the CONTRACTOR unless notice of such
claim shall have been given by the
CONTRACTOR to the EngineerinCharge and
the Site Engineer in the manner and within
the time aforesaid and the CONTRACTOR
SHALL be deemed to have waived any and all
claims and all his rights in respect of any
claim not notified to the EngineerinCharge
and the Site Engineer in writing in the manner
and within the time aforesaid.
// 4 //
6.6.2.0 The EngineerinCharge and/or the Site
Engineer shall be under no obligation to reply
to any notice of claim given or claim made by
the CONTRACTOR within the provisions
aforesaid or otherwise or to reject the same
and no omission or failure on the part of the
EngineerinCharge or Site Engineer to reject
any claim made or notified by the
CONTRACTOR or delay in dealing therewith
shall be deemed to be an admission by the
OWNER of the validity of such claim or waiver
by the OWNER of any of its rights in respect
thereof, with the intent that all such claims
otherwise valid within the provisions of Clause
6.6.1.0 read with Clauses 6.6.3.0 and 6.6.3.1
shall be dealt with/considered by the OWNER
at the time of submission of the Final Bill.
6.6.3.0 Any claims of the CONTRACTOR notified in accordance with the provision of Clause 6.6.1.0
hereof as shall remain at the time of preparation of Final Bill by the CONTRACTOR shall be
separately included in the Final Bill prepared
by the CONTRACTOR in the form of a Statement of Claims attached thereto, giving particulars of the nature of the claim, grounds on
which it is based, and the amount claimed and
shall be supported by a copy(ies) of the
notice(s) sent in respect thereof by the CONTRACTOR to the EngineerinCharge and Site
Engineer under Clause 6.6.1.0 hereof. In so
far as such claim shall in any manner or particular be at variance with the claim notified
by the CONTRACTOR within the provision of
Clause 6.6.1.0 hereof, it shall be deemed to be
a claim different from the notified claim with
consequence in respect thereof indicated in
Clause 6.6.1.0 hereof, and with consequences
in respect of the notified claim as indicated in
Clause 6.6.3.1 hereof.
6.6.3.1 The OWNER shall not anywise be liable in respect of any notified claim not specifically reflected in the Final Bill in accordance with the
provisions of Clause 6.6.3.0 hereof and any
and all notified claims not specifically reflected
and included in the Final Bill in accordance
// 5 //
with the provisions of Clause 6.6.3.0 hereof
shall be deemed to have been waived by the
CONTRACTOR. Further the OWNER shall have
no liability in respect thereof and the CONTRACTOR shall not be entitled to raise or include in the Final Bill any claim(s) other than
a notified claim conforming in all respects and
in accordance with the provisions of Clause
6.6.3.0 hereof.
6.6.4.0 No claim(s) shall on any account be made by
the CONTRACTOR after the Final Bill, with the
intent the Final Bill prepared by the CONTRACTOR shall reflect any and all notified
claims whatsoever of the CONTRACTOR
against the OWNER arising out of or in connection with the Contract or work performed
by the CONTRACTOR thereunder or in relation
thereto, and the CONTRACTOR shall notwithstanding any enabling provision under any law
or Contract and notwithstanding any right of
claim in quantum meruit that the CONTRACTOR could have in respect thereof, be deemed
to have waived any and all such claims not included in the Final Bill and to have absolved
and discharged the OWNER from and against
the same, even if in not including the same as
aforesaid, the CONTRACTOR shall have acted
under a mistake of law or fact.
6.6.5.0 Notwithstanding the existence of any claim by
the CONTRACTOR in terms hereof or otherwise, the CONTRACTOR shall continue and be
bound to continue and perform the works to
completion in all respects according to the
Contract (unless the Contract or works be priorly determined by the OWNER in terms
hereof) and shall remain liable and bound in
all respects under the Contract.
6.6.6.0 The payment of any sum on account to the
CONTRACTOR during the performance of any
work or item of work in respect of which a
claim has been notified by the CONTRACTOR
in terms of Clause 6.6.1.0 hereof or the making or negotiation of any interim arrangements
in respect of the performance of such work or
item of work by the OWNER, shall not be
// 6 //
deemed to be an acceptance of the related
claim by the OWNER, or any part or portion
thereof with the intent that any such payment
shall constitute merely an interim facility or
interim assistance to the CONTRACTOR, and
not an obligation upon the OWNER.
6.7.0.0 DISCHARGE OF OWNER’S LIABILITY
6.7.1.0 The acceptance by the CONTRACTOR of any
amount paid by the OWNER to the CONTRACTOR in respect of the final dues of the CONTRACTOR under the Final Bill upon condition
that the said payment is being made in full
and final settlement of all said dues to the
CONTRACTOR shall, without prejudice to the
notified claims of the CONTRACTOR included
in the Final Bill in accordance with the provisions under Clause 6.6.3.0 hereof and associated provisions thereunder, be deemed to be in
full and final satisfaction of all such dues to
the CONTRACTOR notwithstanding any qualifying remarks, protest or condition imposed or
purported to be imposed by the CONTRACTOR
relative to the acceptance of such payment,
with the intent that upon acceptance by the
CONTRACTOR of any payment made as aforesaid, the Contract (including the arbitration
clause) shall, subject to the provisions of
Clause 6.8.2.0 hereof, stand discharged and
extinguished except in respect of the notified
claims of the CONTRACTOR included in the
Final Bill and except in respect of the CONTRACTOR's entitlement to receive the unadjusted portion of the Security Deposit in accordance with the provisions of Clause 6.8.3.0
hereof on successful completion of the defect
liability period.
6.7.2.0 The acceptance by the CONTRACTOR of any
amount paid by the OWNER to the CONTRACTOR in respect of the notified claims of the
CONTRACTOR included in the Final Bill in accordance with the provisions of Clause 6.6.3.0
hereof and associated provisions thereunder,
upon the condition that such payment is being
made in full and final settlement of all the
claims of the CONTRACTOR shall, subject to
the provisions of Clause 6.7.3.0 hereof, be
deemed to be in full and final satisfaction of all
// 7 //
claims of the CONTRACTOR notwithstanding
any qualifying remarks, protest or condition
imposed or purported to be imposed by the
CONTRACTOR relative to the acceptance of
such payment with the intent that upon acceptance by the CONTRACTOR of any payment made as aforesaid, the Contract (including the arbitration clause) shall stand discharged and extinguished insofar as relates to
and/or concerns the claims of the CONTRACTOR.
6.7.3.0 Notwithstanding anything provided in Clause
6.7.1.0 and/or Clause 6.7.2.0 hereof the CONTRACTOR shall be and remain liable for defects in terms of Clause 5.6.0.0 hereof and for
the indemnity to the OWNER in terms of
Clause 6.8.2.0, and shall be and remain entitled to receive the unadjusted balance of the
Security Deposit remaining in the hands of the
OWNER in terms of Clause 6.8.3.0 hereof.
xxx xxx xxx
9.0.0.0 ARBITRATION
9.0.1.0 Subject to the provisions of Clauses 6.7.1.0,
6.7.2.0 and 9.0.2.0 hereof, any dispute arising
out of a Notified Claim of the CONTRACTOR
included in the Final Bill of the CONTRACTOR
in accordance with the provisions of Clause
6.6.3.0 hereof, if the CONTRACTOR has not
opted for the Alternative Dispute Resolution
Machinery referred to in Clause 9.1.1.0 hereof,
and any dispute arising out of any Claim(s) of
the OWNER against the CONTRACTOR shall
be referred to the arbitration of a Sole Arbitrator selected in accordance with the provisions
of Clause 9.0.1.1 hereof. It is specifically
agreed that the OWNER may prefer its
Claim(s) against the CONTRACTOR as
counterclaim(s) if a Notified Claim of the
CONTRACTOR has been referred to arbitration. The CONTRACTOR shall not, however, be
entitled to raise as a setoff defence or
counterclaim any claim which is not a Notified Claim included in the CONTRACTOR's Final Bill in accordance with the provisions of
Clause 6.6.3.0 hereof.
// 8 //
9.0.1.1 The Sole Arbitrator referred to in Clause
9.0.1.0 hereof shall be selected by the CONTRACTOR out of a panel of 3 (three) persons
nominated by the OWNER for the purpose of
such selection, and should the CONTRACTOR
fail to select an arbitrator within 30 (thirty)
days of the panel of names of such nominees
being furnished by the OWNER for the purpose, the Sole Arbitrator shall be selected by
the OWNER out of the said panel.
9.0.2.0 Any dispute(s) or difference(s) with respect to
or concerning or relating to any of the following matters are hereby specifically excluded
from the scope, purview and ambit of this Arbitration Agreement with the intention that
any dispute or difference with respect to any of
the said following matters and/or relating to
the Arbitrator's or Arbitral Tribunal's jurisdiction with respect thereto shall not and cannot
form the subject matter of any reference or
submission to arbitration, and the Arbitrator
or the Arbitral Tribunal shall have no jurisdiction to entertain the same or to render any decision with respect thereto, and such matter
shall be decided by the General Manager prior
to the Arbitrator proceeding with or proceeding
further with the reference. The said excluded
matters are:
(i) With respect to or concerning the scope or
existence or otherwise of the Arbitration Agreement;
(ii) Whether or not a Claim sought to be referred to arbitration by the CONTRACTOR is a
Notified Claim;
(iii) Whether or not a Notified Claim is included
in the CONTRACTOR's Final Bill in accordance
with the provisions of Clause 6.6.3.0 hereof.
(iv) Whether or not the CONTRACTOR has
opted for the Alternative Dispute Resolution
Machinery with respect to any Notified Claim
included in the CONTRACTOR's Final Bill.
// 9 //
9.0.3.0 The provisions of the Indian Arbitration &
Conciliation Act, 1996 and any reenactment(s) and/or modification(s) thereof
and of the Rules framed thereunder shall apply to arbitration proceedings pursuant hereto
subject to the following conditions:
(a) The Arbitrator shall give his Award separately in respect of each Claim and CounterClaim; and
(b) The Arbitrator shall not be entitled to review any decision, opinion or determination
(howsoever expressed) which is stated to be final and/or binding on the CONTRACTOR in
terms of the Contract Documents.”
4.2. As per the contract entered into between the
parties, the designated date for commencement of
the project was the date of issuance of FOA i.e.
03.03.2010, and that the scheduled date of
completion was 02.10.2011. It appears that the
execution of the project was delayed, as a result of
which the project was completed only on
28.12.2015. The NCCL was issued a completion
certificate by the IOCL indicating the date of
completion of the project as 28.12.2015. In view of
the delay in completion of the project beyond the
scheduled date, the NCCL made a request for
extension of time vide the communication dated
23.05.2016. While the EOT requests were pending
with the IOCL, the NCCL submitted its final bill
dated 05.08.2016 to the EngineerInCharge
appointed under the contract between the parties.
// 10 //
According to the NCCL, the NCCL in its final bill
dated 05.08.2016 made a specific reference to the
Notified Claims. There were correspondences
between the EngineerInCharge and
Thyssenkrupp Industrial Solutions India (P) Ltd.
(hereinafter referred to as “TKIS”) pending
settlement of the final bill and the request for
Extension of Time (EOT). The NCCL responded to
the communication dated 01.11.2016 by the TKIS,
vide its response dated 02.11.2016. It appears that
the NCCL conveyed to TKIS that if its request for
EOT were considered favorably and if price
adjustment does not exceed 4%, then, all its
extra/additional claims including Notified Claims
submitted by it through various communications
and the final bill should be treated as withdrawn.
4.3. The TKIS having received the aforesaid
communication from the NCCL, made its
recommendations visàvis the request for EOT
made by the NCCL. It appears that thereafter, TKIS
in its communication dated 13.01.2017, informed
NCCL that it had approved EOT for the period
between 03.10.2011 to 03.11.2015, however,
without price discount as per Clause 4.4.0.0 of the
General Conditions of Contract (hereinafter
referred to as “GCC”) and that for the period falling
// 11 //
between 04.11.2015 to 28.12.2015 which covered
the period of 55 days, it had concluded that the
delay was attributable to NCCL. Accordingly, TKIS
conveyed to NCCL that for the later period, as per
Clause 4.4.2.0 of the GCC, a price adjustment
discount of 4% would be applicable.
4.4. It is the case on behalf of NCCL that being
aggrieved, it wrote to the IOCL on 23.01.2017 to
reconsider its decision and accord EOT upto the
date of completion i.e. 28.12.2015 without making
any adjustment towards price as indicated in the
communication dated 13.01.2017.
4.5. That, thereafter, the IOCL released a sum of
Rs.4,53,04,021/, the amount calculated as per
the communication dated 13.01.2017, after
making due adjustments towards taxes etc.
4.6. It appears that subsequently and after a period of
6&1/2 months (after the settlement of the claim)
and after receiving the final bill payment 8 days
earlier, on 08.05.2017, vide communication dated
16.05.2017, NCCL reneged on the letter of
02.11.2016 and alleged that it was made to
withdraw its claim under coercion and it had
withdrawn its Notified Claims as TKIS vide its
communication dated 01.11.2016, had indicated
// 12 //
that the review of the final bill and request for EOT
would be considered only if it gave up its insistence
on its Notified Claims being considered.
4.7. That IOCL sent its response vide communication
dated 06.06.2017, wherein it stated that none of
the claims mentioned in the final bill were Notified
Claims.
4.8. In the above backdrop, NCCL invoked the
arbitration clause contained in the Agreement on
01.07.2017. That, the IOCL, in accordance with
Clause 9.0.2.0 referred the matter regarding
arbitrability of NCCL’s claims to the General
Manager on 12.07.2017.
4.9. Vide the communication / letter dated 10.11.2017,
the General Manager held that the claims cannot
be referred to arbitration and that the Arbitration
Agreement itself does not survive on account of
NCCL withdrawing its Notified Claims. The General
Manager held that therefore there exist no dispute
to be referred to arbitration.
4.10.Thereafter the respondent – NCCL approached the
Delhi High Court by filing Arbitration Petition
No.115/2018 under Section 11(6) of the
Arbitration Act for appointment of sole Arbitrator.
The said petition was opposed by the IOCL on a
// 13 //
number of grounds. However, by overruling all the
objections raised on behalf of the appellant – IOCL,
by the impugned judgment and order, the High
Court has allowed the said arbitration petition and
appointed the sole Arbitrator.
4.11.Impugned judgment and order passed by the High
Court dated 08.02.2019 in Arbitration Petition
No.115/2018 is the subject matter of present Civil
Appeal No.341/2022 (arising out of Special Leave
Petition No.13161/2019).
5. With respect to other four contracts between the same
parties and with same arbitration clauses, the NCCL’s
claims were sent to the General Manager under Clause
9.0.2.0 of the GCC. So far as the Civil Appeal arising out
of SLP No.13408/2019 is concerned, the NCCL did not
approach the General Manager but the Arbitration
Petition filed before the High Court was forwarded by the
IOCL to the General Manager for its determination
under Clause 9.0.2.0 of the GCC. That, in all the
remaining four cases (Civil Appeal Nos.342/2022 to
345/2022), the General Manager declared that none of
the claims were Notified Claims.
6. Thereafter the NCCL approached the High Court by way
of Arbitration Petition Nos.115/2018, 356/2018,
116/2018, 407/2018 and 406/2018. By the impugned
// 14 //
judgment and orders, the High Court has allowed all the
respective applications under Section 11(6) of the
Arbitration Act and by different impugned judgment and
orders, has appointed the sole Arbitrator. Impugned
judgment and orders passed by the High Court is the
subject matter of Civil Appeal Nos.341/2022 to
345/2022.
7. Shri K.K. Venugopal, learned Attorney General has
appeared on behalf of the appellant – IOCL and Shri
Ranjith Kumar, learned Senior Advocate has appeared
on behalf of the respondent – NCCL.
8. Shri K.K. Venugopal, learned Attorney General
appearing on behalf of the IOCL has vehemently
submitted that in the present case both the parties are
governed by the terms of the contract entered into
between the parties viz. the GCC. That in fact, both the
parties are governed by the procedure to be followed in
case of dispute between the parties, more particularly
contained in the GCC and the arbitration clause.
8.1 It is further submitted by the learned Attorney General
that party autonomy is the backbone of arbitration and
the terms of the contract have to be interpreted in the
way the parties wanted and intended them to be. In this
regard reliance is placed upon the decision of this Court
in the case of Centrotrade Minerals & Metal Inc. v.
// 15 //
Hindustan Copper Ltd. reported in (2017) 2 SCC 228
(Paras 3842).
8.2 It is submitted by the learned Attorney General that
there are three categories of contracts which could arise
for consideration, which can be summarized as under:
(i) Where no arbitration agreement exists at all. As the
arbitration agreement itself is an independent contract
and is consensual in nature, it is left to the parties to
include an arbitration agreement in the underlying
contract, or not to include it. If no arbitration agreement
exists in a contract, the only option if a dispute arises
for either party is to go by way of a suit;
(ii) An arbitration agreement can exist in the
underlying contract or outside the contract, which is
absolute in terms. This is the standard arbitration
clause, and would be in the nature of “where any
dispute arises between the parties in relation to the
interpretation or implementation of this contract, it shall
be referred to arbitration under the Arbitration and
Conciliation Act, 1996...” This would be an
UNRESTRICTED or ABSOLUTE arbitration clause.
In such a case, in the background of Section 11(6A), no
question of the Court declining to refer the matter to
arbitration would arise, if it finds that the arbitration
// 16 //
agreement exists and is valid. In such a case, every
dispute between the parties has to be referred to
arbitration because Section 11(6A) would mandate this;
(iii) The third category would be where the parties
agree to have an arbitration clause but also
consensually agree that certain specified disputes alone
will be the subject of arbitration. This would mean that
no arbitration clause exists in regard to all other
disputes, and no arbitration clause would exist in
regard to the ‘excepted’ or ‘excluded’ disputes. In such a
case, Section 11(6A) itself cannot be invoked as no
arbitration clause exists in regard to these other
disputes. This would be a RESTRICTED arbitration
clause.
8.3 It is further submitted by the learned Attorney General
that when all the conditions mentioned in the GCC are
satisfied and the procedure is followed and only with
respect to the restricted arbitration clauses and with
respect to the Notified Claims only the dispute between
the parties can be referred to the arbitration.
8.4 It is submitted that there are umpteen number of
examples of restricted arbitration clauses. Reliance is
placed on the decision of this Court in the case of
United India Insurance Co. Ltd. v. Hyundai Engg. &
Construction Co. Ltd. reported in (2018)17 SCC 607,
// 17 //
where the arbitration clause expressly stated that where
a claim is made against the insurer and the insurer
denies its liability, no reference to arbitration can take
place. In support of the above submission, reliance is
placed on following decisions of this Court:
(1) Vidya Drolia v. Durga Trading Corpn.
[(2021)2 SCC 1, Paras 113116)
(2) Garware Wall Ropes Ltd. vs. Coastal Marine
Constructions & Engg.
[(2019) 9 SCC 209, Paras 2829)
(3) Oriental Insurance Co. Ltd. v. Narbheram
Power & Steel (P) Ltd.
[(2018) 6 SCC 534, Paras 10, 23]
8.5 It is submitted by the learned Attorney General that in
the aforesaid decisions, this Court had occasion to
consider the applicability of Section 11(6A) and its
impact.
8.6 It is submitted that in the case of Garware (supra), it is
observed and held that where the underlying contract
including the arbitration clause is not stamped, in such
a case, the arbitration clause exists in fact but DOES
NOT EXIST IN LAW. That in other words, Section 11(6
A) will not be a Bar for the Court holding that as the
arbitration clause does not cover the particular dispute,
Section 11(6A) will not apply as there is no arbitration
// 18 //
clause in that regard and therefore, no reference to
arbitration can be made.
8.7 It is submitted that in the case of Vidya Drolia (supra),
this Court had considered various aspects with respect
to the restricted arbitration clause. But in the case of
unrestricted clauses, all issues raised by the contracting
parties will have to be referred to arbitration, because of
Section 11(6A). However, the instant case is a case of a
restricted arbitration clause that specifically excludes
certain issues from arbitration, as a result of which, no
arbitration clause exists for those ‘other’ or ‘excepted’
disputes and hence, the question of referring those
disputes would not arise. That in the case of Vidya
Drolia (supra), the Arbitration Agreement itself sets out
what is excluded from arbitration. Therefore, it was held
that Section 11(6A) would not stand in the way of
making a reference.
8.8 It is further submitted by learned Attorney General that
in the present case the respondent NCCL received the
amount of final bill in full settlement of their claims.
That in the present case the arbitration clause itself
states that where the final bill amount has been received
by the party, or where a sum has been received on
account of Notified Claims, the arbitration clause itself
stands extinguished. Therefore, the fact that amount of
final bill having been received in full settlement cannot
// 19 //
be the subject matter of reference by any specific
stipulation in the contract.
8.9 Learned Attorney General has taken us to the relevant
clauses of the GCC more particularly Clauses 1.21.0.0,
6.6.0.0, 6.6.1.0, 6.6.2.0, 6.6.3.0, 6.6.3.1, 6.6.4.0,
6.6.5.0, 6.6.6.0, 6.7.0.0, 6.7.1.0, 6.7.2.0, 6.7.3.0,
9.0.0.0, 9.0.1.0, 9.0.1.1, 9.0.2.0 and 9.0.3.0. It is
contended that as per Clause 9.0.1.0, the only matter to
which a reference to arbitration can be sought is a
“Notified Claim” included in the final bill and to no other
dispute. That all disputes other than Notified Claims
included in the final bill, have to be pursued by way of a
suit. The expression, “Notified Claim” is defined in
Clause 1.21.0.0 of the GCC.
8.10 It is urged that only those Notified Claims which are
notified in accordance with provisions of Clause 6.6.1.0,
can be referred to arbitration.
8.11 It is submitted that the parties are at liberty to provide
within the contract a departmental machinery for
resolution of certain matters, the determination of which
will be outside the scope of arbitration. That such
departmental machinery, being the will of the parties as
embodied in the contract, must be respected and given
effect to. In support of the above submissions, reliance
is placed on the following decisions of this Court:
// 20 //
(i) Food Corporation of India v. Sreekanth Transport
(1999)4 SCC 491 (Paras 2, 3)
(ii) Harsha Constructions v. Union of India
(2014) 9 SCC 246 (Paras 14, 18, 19)
(iii) Mitra Guha Builders (India) Company v. Oil and
Natural Gas Corporation Ltd.
(2020) 3 SCC 222 (Paras 23, 24, 26, 30)
8.12 The learned Attorney General has also relied upon the
following decisions of the Delhi High Court and Gauhati
High Courts dealing with identical clause in cases where
the IOCL was a party and in which the Delhi High Court
and Gauhati High Court have expressly interpreted the
very Clause 9.0.1.0 and 9.0.2.0.
(i) China Petroleum Pipeline Bureau v. Indian Oil
Corporation Ltd. [ARB.A. (COMM.) 35/2019,
decision dated 10.01.2020]
(ii) Srico Projects Pvt. Ltd. v. Indian Oil Foundation
[ARB. PET. 276/2016 decided on 09.01.2017 along
with order dated 03.07.2017]
(iii) Institute of Geoinformatics (P) Ltd. v. Indian Oil
Corporation Ltd. [ARB. PET. 175/2012 decided on
19.05.2015]
(iv) IOT Infrastructure and Energy Service v. Indian Oil
Corporation Ltd. [ARB. PET. 334/2014 decided on
12.02.2015]
(v) Bongaigaon Refinery v. M/s. Buildworth Pvt. Ltd.
// 21 //
[Arb.Appeal 10/2006 before Gauhati High Court]
8.13 It is submitted that the Special Leave Petitions against
the decision in the case of China Petroleum Pipeline
Bureau (supra) and Srico Projects Pvt. Ltd. (supra) have
been dismissed by this Court.
8.14 It is further submitted by learned Attorney General that
in the present case the final bill payment had been
made to the respondent and accepted by it pursuant to
an understanding between the parties by which the
respondent expressly waived its Notified Claims. It is
submitted that the arbitration clause itself is subject to
Clauses 6.7.1.0 and 6.7.2.0. It is submitted that Clause
6.7.2.0 dealing with “Notified Claims” expressly declares
that the acceptance of any amount by the contractor in
respect of the Notified Claims shall result in full and
final satisfaction of the claims by the contractor in
respect of the Notified Claims and hence, the contract,
including the arbitration clause, shall stand discharged
and extinguished. This is as per Clause 6.7.2.0 itself,
notwithstanding any qualifying remarks, protest or
condition imposed or purported to be imposed by the
contractor relative to the acceptance of such payment.
8.15 It is submitted that applying these principles to the
present case, NCCL’s express statement dated
02.11.2016 is required to be appreciated and/or
// 22 //
considered. That pursuant to the said statement by the
NCCL, the IOCL (petitioner) levied a price adjustment of
only 4% as opposed to 10%; and the respondent
expressly withdrew its Notified Claims. It is submitted
that the IOCL also paid the dues as per the final bill.
The Notified Claims, having been withdrawn, therefore,
could not more be the subject matter of any reference to
arbitration. It is submitted that as a result of the
acceptance by the NCCL of the amount paid pursuant to
its final bill, and the Notified Claims having been
withdrawn, and the result of Clauses 6.7.1.0 and
6.7.2.0, the contract, including the arbitration clause
stands discharged and extinguished and therefore,
subsequently, no reference to arbitration could be made.
8.16 It is submitted that it is only 6½ months later, on
16.05.2017 and after receiving the final bill payment 8
days earlier on 08.05.2017, that the NCCL reneged on
its letter withdrawing its demand in regard to Notified
Claims. It is submitted that the reason why the NCCL
withdrew their demand for payment of the full amount
of final bill including Notified Claims is that if 10% has
been deducted due to the delay, an amount of Rs.14.8
Crores would have been deducted from the payment of
NCCL. It is submitted that having received Rs.151
Crores against the contract of Rs.148 Crores, the NCCL
was well aware that in such an eventuality, it would
have received no amount against the final bill and its
// 23 //
bank guarantee would also have been invoked. That in
fact by withdrawing the demand, the respondent was
now able to get Rs.4.53 Crores as well as the return of
the bank guarantee of Rs.14.8 Crores.
8.17 It is further submitted that Clause 9.0.2.0 of the GCC
specifically excludes certain matters, such as disputes
concerning the scope of the arbitration agreement, viz.,
(i) whether or not a claim is a Notified Claim; (ii) whether
or not a Notified Claim is included in the contractor’s
bill etc.; from the scope, purview and ambit of the
Arbitration Agreement. It is submitted that under subClause (iii) thereof, a Notified Claim covered by a
decision of the General Manager is specifically an
excluded matter. It is submitted that in the present case
the General Manager rejected the demand of the NCCL
in regard to the Notified Claims, particularly as the
demand in regard to ‘Notified Claims’ had been
specifically withdrawn by the NCCL. It is submitted
therefore that viewed from any angle, as no arbitration
clause existed so far as the NCCL is concerned, the High
Court has committed a serious error in referring the
dispute between the parties to Arbitrator and appointing
the Arbitrator.
8.18 Now, so far as the other four cases are concerned, the
learned Attorney General has submitted that in those
four cases the claims were referred / sent to the General
// 24 //
Manager under Clause 9.0.2.0 of the GCC. That in all
the remaining cases the General Manager declared that
none of the claims of the NCCL was a Notified Claim.
Therefore, the claims which are found by the General
Manager not to be Notified Claims are not arbitrable and
are outside the scope and purview of the Arbitration
Agreement. It is submitted that in that view of the
matter, the High Court ought to have dismissed the
applications / petitions filed by the NCCL under Section
11 of the Arbitration Act.
Making above submissions and relying upon
decisions, it is prayed to allow the present appeals and
set aside the respective orders passed by the High Court
referring the dispute between the parties to arbitration
and appointing the sole Arbitrator.
9. Present appeals are vehemently opposed by Shri Ranjith
Kumar, learned Senior Advocate appearing on behalf of
the respondent – NCCL.
9.1 Shri Ranjith Kumar, learned Senior Advocate appearing
for the respondent – NCCL has made following
submissions pointing out the relevant facts which,
according to him, are relevant for deciding the dispute
in present appeals.
(1) That, the parties herein had entered into an
agreement, whereby the respondent NCCL was
// 25 //
tasked with the job of completing the civil,
structural and associated UG Piping works for the
Paradip Refinery;
(2) Due to certain reasons attributable to IOCL, there
was a delay in completion of the works;
(3) In accordance with the GCC, NCCL on 23.05.2016,
applied for extension of time and submitted its
final bill on 05.08.2016;
(4) On 29.07.2016, NCCL issued the No Due
Certificate, however, it also made it clear that the
said Certificate would not include final bill amount,
service tax amount and the Notified Claims due
from IOCL;
(5) The Engineerincharge vide letter dated
01.01.2016, expressly acknowledged the presence
of “Notified Claims” in the final bill and coerced
NCCL to take back its Notified Claims in order to
process its application for EOT;
(6) Under duress, NCCL was constrained to issue a
letter on 02.11.2016 withdrawing its Notified
Claims on the twin condition that the application
for EOT is considered favorably and the price
discount does not exceed 4% of the contract value;
(7) That, the letter dated 02.11.2016 was clearly
conditional and was in the nature of an offer and
not an acceptance;
(8) Vide letter dated 13.01.2017, IOCL informed NCCL
// 26 //
that they had only partially allowed the application
for EOT and a price discount of 4% was applied to
the period for which the application for EOT was
not allowed. Therefore, it is clear that IOCL did not
positively respond to both the conditions stated by
NCCL in its letter dated 02.11.2016;
(9) That, aggrieved by the aforesaid decision, NCCL
without any delay, on 23.01.2017, communicated
that the decision to partially allow its application
for EOT is unacceptable as the same is not in
accordance with the conditional offer given by
NCCL and also since the delay was caused due to
reasons attributable to the IOCL;
(10) Disregarding the aforesaid letter, IOCL on
08.05.2017, unilaterally released the payment
against the final bill, after adjusting the price
discount;
(11) That, NCCL on 16.05.2017 i.e. within 10 days from
the release of the amount, informed IOCL that the
application for price discount is misplaced and its
‘Notified Claims’ still hold good as the conditional
offer of NCCL was not accepted;
(12) Since IOCL miserably failed to provide an
appropriate response within a reasonable period of
time, NCCL invoked the arbitration clause i.e.
Clause 9.0.1.0 of the GCC and submitted its
claims to IOCL;
// 27 //
(13) It is submitted that as per Clause 9.0.1.0 read with
Clause 9.0.2.0 of the GCC, IOCL had to refer the
claims of NCCL to its General Manager and then
the General Manager was to issue a declaration
pursuant to which the arbitration could
commence;
(14) It is submitted that in the claims concerned in four
of the petitions, the determination was made by
the General Manager in an inordinately belated
manner. It is submitted that in 3 out of 5 petitions,
the determination by the General Manager was
made after NCCL filed the arbitration petitions
before the High Court. It is submitted that in a
completely malafide and deceptive manner, IOCL
claims to have made a reference to the General
Manager who determined the nature of claims after
filing of the counter affidavit by NCCL before this
Court.
(15) It is submitted that therefore, as such, IOCL is
attempting to scuttle respondent’s contractual
right to pursue arbitration by bringing on record a
document nearly two years after the respondent
invoked the arbitration clause.
(16) It is submitted that the General Manager’s decision
which is relevant in SLP Nos.13161 and 13183 of
2019 was based on the ground that there was full
and final settlement between the parties. It is
// 28 //
submitted that as the decision of the General
Manager on “Notified Claims” was erroneous,
malafide and on technical grounds, NCCL rightly
approached the High Court of Delhi under Section
11(6) of the Arbitration Act seeking the relief of
appointment of Arbitrator. It is submitted that
therefore the High Court is absolutely justified in
appointing the Arbitrator.
9.2 Shri Ranjith Kumar, learned Senior Advocate appearing
for NCCL has supported the impugned orders passed by
the High Court by making the following broad
submissions:
(1) As per the agreement entered into between the
parties, the General Manager is not permitted to
decide if a claim is barred by virtue of there being
accord and satisfaction or a claim being an
excepted claim.
(2) Under Section 11(6A) of the Arbitration Act, at the
stage of appointment of an arbitrator, the scope of
intervention by the Courts is confined to the
examination of the existence of an arbitration
agreement.
(3) At the stage of appointment of the arbitrator, the
Court cannot look into whether there has been
accord and satisfaction between the parties
(4) At the stage of appointment of arbitrator, the Court
cannot look into whether a claim is an excepted
// 29 //
claim or not.
(5) Contractual clauses cannot be read in a manner
that abridges statutory rights and the doctrine of
mutuality, to confer the power to unilaterally
determine arbitrability of a dispute upon one of the
parties.
(6) As per the doctrine of election, the present
proceedings ought to be dismissed since IOCL has
preferred an application under Section 16(2) and
16(5) challenging the jurisdiction of the Arbitral
Tribunal.
9.3 On an interpretation of the Clauses of the GCC, Shri
Ranjith Kumar, learned Senior Advocate appearing for
the respondent NCCL has submitted that a bare perusal
of the relevant clauses of the GCC would indicate that
the General Manager of IOCL is neither entitled to
examine whether a “Notified Claim” is an ‘excepted
claim’ nor can he look into the issue whether there is
accord and satisfaction between the parties.
9.4 It is submitted that Clause 9.0.1.0 is subject to Clauses
6.7.1.0, 6.7.2.0 and 9.0.2.0. Further, Clause 9.0.2.0
creates a machinery whereby IOCL has unbridled power
conferred upon its General Manager to certify if a claim
is capable of being referred to arbitration. The said
clause, according to IOCL vests the sole discretion of
deciding the arbitrability of claims on the General
Manager. It is submitted that, as such, the
// 30 //
interpretation of the Clause as suggested by IOCL, is in
derogation of not only the arbitrator’s power to decide
arbitrability, but also the Court’s power under Section
11 of the Arbitration Act.
9.5 It is submitted that the said Clause would indicate that
the General Manager is only supposed to see if the claim
raised by the respondent is (i) a Notified Claim as
defined under Clause 1.21.0.0 r/W. Clause 6.6.1.0; and
(ii) whether the Notified Claim is included in the final bill
in accordance with Clause 6.6.3.0. That the General
Manager is not empowered under the said Clause to
state that a claim is not arbitrable due to full and final
settlement between the parties or due to a claim being
an excepted claim.
9.6 It is submitted that in the present case, the IOCL has
admitted that the claims raised by the respondent are
‘Notified Claims’ and this fact has never been disputed
by the IOCL or its General Manager. It is submitted that
even the second condition is also fulfilled as the
respondent’s final bill includes its Notified Claims. It is
submitted that thus the only logical conclusion which
follows is that the Notified Claims raised by the
respondent should have been referred to arbitration.
However, the General Manager of the IOCL, in two
cases, denied referring the Notified Claims to arbitration
on the ground that there was full and final settlement
// 31 //
between the parties, and in other three cases the
General Manager has denied referring the Notified
Claims to arbitration on the ground that they are
‘excepted claims’.
9.7 It is submitted that as per the GCC, the General
Manager is not entitled to resist the reference of a
Notified Claim to arbitration on the ground of accord
and satisfaction. That the aspect pertaining to full and
final settlement between the parties, forms part of
Clauses 6.7.1.0 and 6.7.2.0 and not of Clause 9.0.2.0.
That, in fact, Clause 6.7.1.0 expressly provides that
upon payment of sums under the final bill, there shall
be full and final settlement, without prejudice to the
Notified Claims of the contractor included in the final
bill. It is submitted that therefore, even after the
payment of money on 08.05.2017, Notified Claims are
neither settled nor is there full and final settlement in
respect of Notified Claims. It is submitted that insofar as
‘excepted claims’ are concerned, as per Clause 9.0.2.0,
once the General Manager comes to a decision that a
claim is a Notified Claim and the same is included in the
final bill, he is duty bound to refer the claim to
arbitration. It is submitted that therefore the reasoning
behind the decision rendered by the General Manager
that the claims are not Notified Claims is not only
unsustainable, but is also ex facie contrary to Clause
9.0.2.0. It is submitted that Clause 9.0.2.0 does not
// 32 //
render the decision of the General Manager final.
9.8 It is further submitted that vide the Amendment Act,
2015, section 11(6A) has been inserted by virtue of
which, the scope of intervention at Section 11 stage is
very narrow. Reliance is placed upon the decision of this
Court in the case of Duro Felguera S.A. v. Gangavaram
Port Limited [(2017) 9 SCC 729]. It is submitted that
after insertion of Section 11(6A), the scope of
intervention by the Court at the stage of appointment of
Arbitrator is narrowed down and the Courts may have to
now only examine the existence of a valid arbitration
agreement. That in the aforesaid decision it is held that
the legislative purpose is essentially to minimize the
Court’s intervention at the stage of appointment of
Arbitrator and that the intention as incorporated in
Section 11(6A) ought to be respected is the submission.
9.9 It is submitted that despite the above binding decision,
in the subsequent decision in the case of United India
Insurance Co. Ltd. v. Antique Art Exports (P) Ltd.
[(2019) 5 SCC 362], a coordinate Bench of this Court
took the view that once a claim is settled, it leaves no
arbitral dispute subsisting under the agreement to be
referred to the Arbitrator.
9.10 It is submitted that the conflicting decisions were
considered and the issue has now been settled by a
// 33 //
Three Judges Bench of this Court in a subsequent
decision rendered in the case of Mayavati Trading
Private Limited v. Pradyuat Deb Burman [(2019) 8
SCC 714]. That after considering in detail the 246th Law
Commission Report; the report of the HighLevel
Committee regarding institutionalization of arbitration
in India and the Statement of Objects and Reasons of
the 2015 Amendment Bill, it is held that post2015, the
scope of the Courts’ powers at the stage of appointment
of Arbitrator is confined to the examination of the
existence of the arbitration agreement. It is submitted
that the decision of this Court in the case of Mayavati
Trading Private Limited (supra) has been subsequently
followed by this Court in a recent decision in the case of
Vidya Drolia (supra).
9.11 Shri Ranjith Kumar, learned Senior Advocate appearing
on behalf of the respondent has also relied upon the
following decisions of this Court in support of his
submissions of applicability of Section 11(6A) and a
very limited jurisdiction of the Courts while considering
an application of Section 11(6A) of the Arbitration Act
post2015.
(1) Uttarakhand Purv Sainik Kalyan Nigam Ltd. v.
Northern Coal Field Ltd.
(2020)2 SCC 455
(2) BSNL & Anr. v. Nortel Networks India Pvt. Ltd.
(2021)5 SCC 738
// 34 //
(3) Pravin Electricals (P) Ltd. v. Galaxy Infra & Engg.
(P) Ltd.
(2021)5 SCC 671
(4) Sanjiv Prakash v. Seema Kukreja
(2021)9 SCC 732
9.12 It is further submitted that although 2019 Amendment
to the Arbitration Act has deleted Section 11(6A), this
Court in the case of Vidya Drolia (supra) has clarified
that the rationale behind the insertion of Section 11(6A)
of the Arbitration Act would continue to apply and guide
the Courts on its scope of jurisdiction at stage one, that
is, the prearbitration stage.
9.13 It is further submitted by learned Senior Advocate
appearing for the respondent NCCL that as held by this
Court in the case of Vidya Drolia (supra) as well as in
the case of Swiss Timing Limited v. Commonwealth
Games 2010 Organizing Committee [(2014) 6 SCC
677], the role of a Court is to assist and support
arbitration and leave a substantive part of the
adjudication to the arbitral Tribunal. It is submitted
therefore that at the stage of an application filed under
Section 11, the Court is only supposed to look as to,
whether, a valid arbitration agreement exists. It is
submitted that therefore the scope of intervention by the
Court is restricted at the stage of appointment of
// 35 //
Arbitrator and it can neither examine whether certain
claims are ‘excepted’ nor can it look into the issue of
whether there is “accord and satisfaction”.
9.14 It is further submitted by learned Senior Advocate
appearing for the respondent NCCL that in cases where
the claims are rejected by the General Manager on the
ground that there was “accord and satisfaction” between
the parties and hence, not referable to arbitration, in the
instant case the respondent has disputed petitioner’s
contention on “accord and satisfaction” even before the
payment of final bill. It is submitted that therefore the
issue whether “accord and satisfaction” existed between
the parties is virtual in nature and examination of the
same would require detailed perusal of the evidence by
the Arbitral Tribunal. That in any event, pursuant to the
introduction of Section 11(6A), the Court has to restrict
itself to the issue of existence of the Arbitration
Agreement at Section 11 stage and cannot delve into the
issue of “accord and satisfaction” is the submission.
9.15 Relying upon the decisions of this Court in the case of
Ambica Construction v. Union of India reported in
(2006) 13 SCC 475 and R.L. Kalathia & Co. v. State
of Gujarat reported in (2011) 2 SCC 400, it is
submitted that as observed by this Court in the
aforesaid two decisions, in many instances, contractors
are coerced to issue a nodues certificate, without which
// 36 //
no amount would be released. It is submitted that in the
aforesaid decision it is observed that merely because the
contractor has issued “No Dues Certificate”, if there is
an acceptable claim, the Court cannot reject the same
on the ground of issuance of “No Dues Certificate”.
9.16 It is further submitted that the question whether a
Notified Claim is an ‘excepted claim’, is within the
exclusive domain of the Arbitrator to be answered.
Reliance is placed on the decision of this Court in the
case of BSNL v. Motorola India (P) Ltd. reported in
(2009) 2 SCC 337 and National Insurance Co. Ltd. v.
Boghara Polyfab Pvt. Ltd. reported in (2009) 1 SCC
267 (even prior to 2015 Amendment to the Arbitration
Act) as well as in the case of Zostel Hospitality (P) Ltd.
vs. Oravel Stays (P) Ltd. reported in (2021) 9 SCC
765.
9.17 It is further submitted that Section 11 of the Arbitration
Act expressly confers powers upon the Courts to
determine the existence of an Arbitration Agreement and
subsequently appoint an Arbitrator. It is submitted that
Section 8 confers upon the Courts and judicial
authorities the power to refer the parties to arbitration
when there is an arbitration Agreement. Similarly,
section 16 of the Arbitration Act categorically recognizes
and empowers the Arbitral Tribunal to rule on any
objection raised as against its jurisdiction. It is
// 37 //
submitted that therefore petitioner’s interpretation of
Clause 9.0.2.0 of the GCC qua the purported finality of
the determination of its General Manager, seeks to
usurp the statutory powers of the Courts as enshrined
under Sections 8 and 11 and the statutory power of an
arbitral Tribunal as enshrined under Section 16.
9.18 It is further submitted that insofar as the claims
concerned in other four petitions (except the lead
matter), the determination was made after an inordinate
delay. That in 3 out of 5 petitions, the determination by
the General Manager was made after the respondent
filed the Arbitration Petitions before the High Court.
That in SLP No.13408/2019, even no reference to the
General Manager was made until the filing of the
Arbitration Petition before the High Court. That
therefore the General Manager’s decision in the
aforesaid four SLPs is inefficacious as the determination
has been made not only thirty days after the submission
of the claim, but also after the arbitration petitions were
filed before the High Court. Reliance is placed upon the
decisions of this Court in the case of Datar Switchgears
Ltd. v. Tata Finance Ltd. reported in (2000) 8 SCC
151 (Paras 18 and 19).
9.19 It is further submitted by Shri Ranjith Kumar, learned
Senior Advocate appearing for respondent NCCL that
in the present case, the petitioner had filed an
// 38 //
application challenging the jurisdiction of the Arbitral
Tribunal under Sections 16(2) and 16(5) of the
Arbitration Act before the Arbitral Tribunal on
10.06.2019, which is, after filing of the present petition
and before the issuance of notice by this Court on
03.07.2019. That the petitioner has not disclosed the
same and has suppressed this factum of pursuing two
remedies simultaneously. It is submitted that therefore
as the petitioner has elected to pursue the proceeding
before the Arbitral Tribunal and as per the doctrine of
election of remedies, the petitioner ought not to be
permitted to continue the present proceedings before
this Court.
Making above submissions, it is prayed to dismiss
the present appeals.
10. We have heard learned Senior Advocates appearing for
the respective parties at length.
10.1 By the impugned orders the High Court in exercise of
powers under Section 11(6) of the Arbitration Act has
appointed the Arbitrators to adjudicate and resolve the
disputes between the parties arising out of the
respective contracts. The respective orders passed by
the High Court appointing the Arbitrator in applications
under Section 11(6) of the Arbitration Act are the
subject matter of present appeals.
// 39 //
10.2 It cannot be disputed that both the parties are governed
by the GCC. The GCC are the part of the Agreements /
Contracts between the parties. Under the GCC, the
parties have agreed to resolve the dispute between them
only in terms of the relevant clauses of the GCC referred
to hereinabove. The parties have agreed that certain
specified disputes alone will be the subject of
arbitration.
10.3 In the case of Narbheram Power & Steel (P) Ltd.
(supra), it is observed and held that the parties are
bound by the Clauses enumerated in the policy and the
Court does not transplant any equity to the same by rewriting a clause. It is further observed and held that an
arbitration clause is required to be strictly construed.
Any expression in the clause must unequivocally
express the intent of arbitration. It can also lay the
postulate in which situations the arbitration clause
cannot be given effect to. It is further observed that if a
clause stipulates that under certain circumstances there
can be no arbitration and they are demonstrably clear
then the controversy pertaining to appointment of
Arbitrator has to be put to rest (Paras 1023).
10.4 In the case of Centrotrade Minerals & Metal Inc. (supra),
this Court had an occasion to consider the concept of
party autonomy and it is observed and held that party
autonomy is virtually the backbone of arbitration. It is
// 40 //
further observed and held that party autonomy being
the brooding and guiding spirit in arbitration, the
parties are free to agree on the application of three
different laws governing their entire contract – (1) proper
law of contract; (2) proper law of arbitration agreement
and (3) proper law of the conduct of arbitration. It is
further observed in the said decision that the parties to
an arbitration agreement have the autonomy to decide
not only on the procedural law to be followed but also
the substantive law. The choice of jurisdiction is also left
to the contracting parties.
10.5 In the case of DLF Universal Ltd. & Anr. v. Director,
Town and Country Planning Department, Haryana &
Ors. [(2010) 14 SCC 1], it is observed and held that the
contract is to be interpreted according to its purpose.
The purpose of a contract is the interest, objective,
values, policy that the contract is designed to actualize.
It comprises the joint intent of the parties. It is observed
that it is not an intent of a single party; it is the joint
intent of both the parties and the joint intent of the
parties is to be discovered from the entirety of the
contract and the circumstances surrounding its
formation (Para 13).
10.6 In the case of Rajasthan State Industrial Development
and Investment Corporation & Anr. v. Diamond and
Gem Development Corporation Ltd. & Anr. [(2013) 5
// 41 //
SCC 470], it is observed and held that a party cannot
claim anything more than what is covered by the terms
of the contract, for the reason that the contract is a
transaction between two parties and has been entered
into with open eyes and by understanding the nature of
contract. It is further observed that thus the contract
being a creature of an agreement between two or more
parties has to be interpreted giving literal meanings
unless there is some ambiguity therein. The contract is
to be interpreted giving the actual meaning to the words
contained in the contract and it is not permissible for
the Court to make a new contract, however reasonable,
if the parties have not made it themselves. It is further
observed that the terms of the contract have to be
construed strictly without altering the nature of a
contract as it may affect the interest of either of the
parties adversely (Para 23).
10.7 In the case of Mitra Guha Builders (India) Company
(supra), while interpreting the clause by which the
parties agreed that the decision of the Superintending
Engineer in levying compensation is final and the same
is an ‘excepted matter’ and the determination shall be
only by the Superintending Engineer and the
correctness of his decision cannot be called in question
in the arbitration proceedings and the remedy, if any,
will arise in the ordinary course of law, the Three
Judges Bench of this Court after referring to and
// 42 //
considering the earlier decisions on the point observed
and held that once the parties have decided that certain
matters are to be decided by the Superintending
Engineer and his decision would be final, the same
cannot be the subject matter of arbitration.
10.8 In the case of Harsha Construction (supra), while
interpreting the clause in the agreement by which some
of the disputes were specifically not arbitrable and in
relation to the said disputes the contractor had to
negotiate with the Engineer concerned and if the
contractor was not satisfied with the rate determined by
the Engineer, the contractor was required to follow the
procedure mentioned in the said clause and in this
regard, in paras 18 and 19, it is observed and held as
under:
“18. Arbitration arises from a contract and unless
there is a specific written contract, a contract with
regard to arbitration cannot be presumed. Section
7(3) of the Act clearly specifies that the contract
with regard to arbitration must be in writing. Thus,
so far as the disputes which have been referred to
in Clause 39 of the contract are concerned, it was
not open to the Arbitrator to arbitrate upon the said
disputes as there was a specific clause whereby
the said disputes had been “excepted”. Moreover,
when the law specifically makes a provision with
regard to formation of a contract in a particular
manner, there cannot be any presumption with
regard to a contract if the contract is not entered
into by the mode prescribed under the Act.
// 43 //
19. If a nonarbitrable dispute is referred to an
Arbitrator and even if an issue is framed by the
Arbitrator in relation to such a dispute, in our
opinion, there cannot be a presumption or a
conclusion to the effect that the parties had agreed
to refer the issue to the Arbitrator. In the instant
case, the respondent authorities had raised an
objection relating to the arbitrability of the
aforestated issue before the Arbitrator and yet the
Arbitrator had rendered his decision on the said
“excepted” dispute. In our opinion, the Arbitrator
could not have decided the said “excepted” dispute.
We, therefore, hold that it was not open to the
Arbitrator to decide the issues which were not
arbitrable and the award, so far as it relates to
disputes regarding nonarbitrable disputes is
concerned, is bad in law and is hereby quashed.”
10.9 At this stage, a recent decision of this Court in the case
of Vidya Drolia (supra), which, as such, is postinsertion
of Section 11(6A) of the Arbitration Act, is required to
be referred to. In the said decision it is observed and
held that the issue of nonarbitrability of a dispute is
basic for arbitration as it relates to the very jurisdiction
of the Arbitral Tribunal. An Arbitral Tribunal may lack
jurisdiction for several reasons and nonarbitrability has
multiple meanings. After referring to another decision of
this Court in the case of Booz Allen & Hamiltan Inc. v.
SBI Home Finance Ltd. [(2011) 5 SCC 532 (Para 34)],
it is observed and held that there are facets of nonarbitrability, namely
“(i) Whether the disputes are capable of adjudication
and settlement by arbitration? That is, whether the
disputes, having regard to their nature, could be
resolved by a private forum chosen by the parties (the
// 44 //
Arbitral Tribunal) or whether they would exclusively
fall within the domain of public fora (courts).
(ii) Whether the disputes are covered by the arbitration
agreement? That is, whether the disputes are
enumerated or described in the arbitration agreement
as matters to be decided by arbitration or whether the
disputes fall under the “excepted matters” excluded
from the purview of the arbitration agreement.
(iii) Whether the parties have referred the disputes to
arbitration? That is, whether the disputes fall under the
scope of the submission to the Arbitral Tribunal, or
whether they do not arise out of the statement of claim
and the counterclaim filed before the Arbitral Tribunal.
A dispute, even if it is capable of being decided by
arbitration and falling within the scope of an
arbitration agreement, will not be “arbitrable” if it is
not enumerated in the joint list of disputes referred to
arbitration, or in the absence of such a joint list of
disputes, does not form part of the disputes raised in
the pleadings before the Arbitral Tribunal.”
After referring to and considering in detail the
earlier decisions on the point, more particularly, with
respect to nonarbitrability and the ‘excepted matters’, it
is ultimately concluded in para 76 as under:
“76. In view of the above discussion, we would
like to propound a fourfold test for determining when
the subject matter of a dispute in an arbitration
agreement is not arbitrable:
76.1. (1) When cause of action and subjectmatter
of the dispute relates to actions in rem, that do not
pertain to subordinate rights in personam that arise
from rights in rem.
76.2. (2) When cause of action and subjectmatter
of the dispute affects thirdparty rights; have erga
omnes effect; require centralized adjudication, and
// 45 //
mutual adjudication would not be appropriate and
enforceable;
76.3. (3) When cause of action and subjectmatter
of the dispute relates to inalienable sovereign and
public interest functions of the State and hence mutual
adjudication would be unenforceable;
76.4 (4) When the subjectmatter of the dispute is
expressly or by necessary implication nonarbitrable as
per mandatory statute(s).
76.5 These tests are not watertight
compartments; they dovetail and overlap, albeit when
applied holistically and pragmatically will help and
assist in determining and ascertaining with great
degree of certainty when as per law in India, a dispute
or subject matter is nonarbitrable. Only when the
answer is affirmative that the subject matter of the
dispute would be nonarbitrable.
76.6 However, the aforesaid principles have to be
applied with care and caution as observed in Olympus
Superstructures (P) Ltd.: (SCC p. 669, para 35)
“35. ...Reference is made there to certain
disputes like criminal offences of a public nature,
disputes arising out of illegal agreements and
disputes relating to status, such as divorce,
which cannot be referred to arbitration. It has,
however, been held that if in respect of facts
relating to a criminal matter, say, physical injury,
if there is a right to damages for personal injury,
then such a dispute can be referred to arbitration
(Keir v. Leeman). Similarly, it has been held that a
husband and a wife may refer to arbitration the
terms on which they shall separate, because they
can make a valid agreement between themselves
on that matter (Soilleux v. Herbst, Wilson v.
Wilson and Cahill v. Cahill).”
10.10 On the question, who decides on nonarbitrability of
the dispute, after referring to and considering the
// 46 //
earlier decisions on the point, more particularly, the
decisions in the case of Garware Wall Ropes Ltd.
(supra); Hyundai Engg. & Construction Co. Ltd. (supra)
and Narbheram Power & Steel (P) Ltd. (supra), it is
observed and held that the question of nonarbitrability relating to the inquiry, whether the
dispute was governed by the arbitration clause, can be
examined by the Courts at the reference stage itself
and may not be left unanswered, to be examined and
decided by the Arbitral Tribunal. Thereafter, in para
153, it is observed and held that the expression,
“existence of arbitration agreement” in Section 11 of
the Arbitration Act, would include aspect of validity of
an arbitration agreement, albeit the Court at the
reference stage would apply the prima facie test. It is
further observed that in cases of debatable and
disputable facts and, good reasonably arguable case
etc., the Court would force the parties to abide by the
arbitration Agreement as the Arbitral Tribunal has the
primary jurisdiction and authority to decide the
disputes including the question of jurisdiction and
nonarbitrability. Ultimately in para 154, the
proposition of law is crystallized as under:
“154. Discussion under the heading ‘Who decides
Arbitrability?’ can be crystallized as under:
154.1. Ratio of the decision in Patel
Engineering Ltd. on the scope of judicial review by the
court while deciding an application under Sections 8 or
// 47 //
11 of the Arbitration Act, post the amendments by Act
3 of 2016 (with retrospective effect from 23102015)
and even post the amendments vide Act 33 of 2019
(with effect from 982019), is no longer applicable.
154.2. Scope of judicial review and
jurisdiction of the court under Section 8 and 11 of the
Arbitration Act is identical but extremely limited and
restricted.
154.3. The general rule and principle, in view of
the legislative mandate clear from Act 3 of 2016 and
Act 33 of 2019, and the principle of severability and
competencecompetence, is that the arbitral tribunal is
the preferred first authority to determine and decide all
questions of nonarbitrability. The court has been
conferred power of “second look” on aspects of nonarbitrability post the award in terms of subclauses (i),
(ii) or (iv) of Section 34(2)(a) or subclause (i) of Section
34(2)(b) of the Arbitration Act.
154.3. Rarely as a demurrer the court may
interfere at the Section 8 or 11 stage when it is
manifestly and ex facie certain that the arbitration
agreement is non existent, invalid or the disputes are
nonarbitrable, though the nature and facet of nonarbitrability would, to some extent, determine the level
and nature of judicial scrutiny. The restricted and
limited review is to check and protect parties from
being forced to arbitrate when the matter is
demonstrably “nonarbitrable” and to cut off the
deadwood. The court by default would refer the matter
when contentions relating to nonarbitrability are
plainly arguable; when consideration in summary
proceedings would be insufficient and inconclusive;
when facts are contested; when the party opposing
arbitration adopts delaying tactics or impairs conduct
of arbitration proceedings. This is not the stage for the
court to enter into a mini trial or elaborate review so as
to usurp the jurisdiction of the arbitral tribunal but to
affirm and uphold integrity and efficacy of arbitration
as an alternative dispute resolution mechanism.”
10.11 In the recent decision of this Court in the case of DLF
// 48 //
Home Developers Limited v. Rajapura Homes
Private Limited and Another [2021 SCC Online SC
781] in which this Court also had an occasion to
consider Section 11(6A) of the Arbitration Act and
ultimately has observed, after referring to and
considering the decision of three Judges Bench of this
Court in the case of Vidya Drolia (supra) that the
jurisdiction of the Court under Section 11 of the
Arbitration Act is primarily to find out whether there
existed a written agreement between the parties for
resolution of the dispute and whether the aggrieved
party has made out a prima facie arguable case, it is
further observed that limited jurisdiction, however,
does not denude the Court of its judicial function to
look beyond the bare existence of an arbitration clause
to cut the deadwood. In the said decision, this Court
had taken note of the observations made in the case of
Vidya Drolia (supra) that with a view to prevent
wastage of public and private resources, the Court may
conduct ‘prima facie review’ at the stage of reference to
weed out any frivolous or vexatious claims.
10.12 In the case of Nortel Networks India Pvt. Ltd. (supra),
this Court had an occasion to consider the decision in
the case of Vidya Drolia (supra) and in paras 46, 47
and 53.2, it is observed and held as under:
“46. The upshot of the judgment in Vidya Drolia [Vidya
// 49 //
Drolia v. Durga Corpn., (2021) 2 SCC 1: (2021) 1 SCC
(Civ) 549] is affirmation of the position of law
expounded in Duro Felguera [Duro Felguera, S.A. v.
Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC
(Civ) 764] and Mayavati Trading [Mayavati Trading (P)
Ltd. v. Pradyuat Deb Burman, (2019) 8 SCC 714 : (2019)
4 SCC (Civ) 441], which continue to hold the field. It
must be understood clearly that Vidya Drolia [Vidya
Drolia v. Durga Corpn., (2021) 2 SCC 1: (2021) 1 SCC
(Civ) 549] has not resurrected the preamendment
position on the scope of power as held in SBP & Co. v.
Patel Engg. Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8
SCC 618].
47. It is only in the very limited category of cases,
where there is not even a vestige of doubt that the
claim is ex facie timebarred, or that the dispute is
nonarbitrable, that the court may decline to make the
reference. However, if there is even the slightest doubt,
the rule is to refer the disputes to arbitration,
otherwise it would encroach upon what is essentially a
matter to be determined by the tribunal.
53.2. In rare and exceptional cases, where the claims
are ex facie timebarred, and it is manifest that there is
no subsisting dispute, the Court may refuse to make
the reference.”
11. Applying the law laid down by this Court in the
aforesaid decisions, let us consider the relevant clauses
of the GCC governing the parties and the procedure to
be followed in case of disputes between the parties to
the contract on nonpayment of alleged dues may be on
account of extra payment or compensation in respect of
the works over and above the amounts due in terms of
the contract and/or the dispute on the validity of any
deductions made or threatened by the owner.
// 50 //
11.1 Clause 1.21.0.0 defines “Notified Claims”. It means a
claim of the contractor notified in accordance with the
provisions of Clause 6.6.1.0. As per Clause 6.6.1.0, the
contractor shall have to give notice in writing of his
claim with respect to any extra payment or
compensation in respect of the works over and above
the amounts due in terms of the contract or on the
validity of any deductions made or threatened by the
owner from any running account bills, by giving notice
in writing of his claim in this behalf to the EngineerinCharge and the Site Engineer within ten days from the
date of issue of the orders or instructions relative to any
works for which the contractor claims such additional
payment… etc. Such notice shall give full particulars of
the nature of such claim, grounds on which it is based
and the amount claimed. It also further provides that
the owner shall not in any way be liable to in respect of
any claim by the contractor unless notice of such claim
shall have been given by the contractor to the EngineerinCharge and the Site Engineer. It also further provides
that a contractor shall be deemed to have waived any
and all claims and all his rights in respect of any claim
not notified to the EngineerinCharge and the Site
Engineer in writing in the manner and within the time
(ten days from the date of issue of the orders or
instructions). It further provides that all such claims
otherwise valid within the provisions of Clause 6.6.1.0
// 51 //
read with Clauses 6.6.3.0 and 6.6.3.1 shall have to be
dealt with/considered by the owner at the time of
submission of the Final Bill and that any action on the
part of the owner (EngineerinCharge or Site Engineer)
to reject any claim made or notified by the contractor or
delay in dealing therewith shall be deemed to be an
admission by the owner of the validity of such claim or
waiver by the owner of any of its rights in respect
thereof.
11.2 As per Clause 6.6.3.0, any claims of the contractor
notified in accordance with the provision of Clause
6.6.1.0 and remain due at the time of preparation of
Final Bill by the contractor, shall have to be separately
included in the Final Bill prepared by the contractor in
the form of a Statement of Claims attached thereto,
giving particulars of the nature of the claim, grounds on
which it is based, and the amount claimed and shall be
supported by a copy of the notice sent in respect thereof
by the contractor to the EngineerinCharge and the Site
Engineer under Clause 6.6.1.0. It further provides that
any variance with the claim notified by the contractor
within the provision of Clause 6.6.1.0 shall be deemed
to be a claim different from the Notified Claim with
consequence in respect thereof indicated in Clauses
6.6.1.0 and 6.6.3.1.
11.3 Clause 6.6.3.1 further provides that the owner (IOCL)
// 52 //
shall not in any way be liable in respect of any Notified
Claim not specifically reflected in the Final Bill in
accordance with the provisions of Clause 6.6.3.0. It
further provides that in and all Notified Claims not
specifically reflected and included in the Final Bill in
accordance with the provisions of Clause 6.6.3.0 shall
be deemed to have been waived by the contractor and
the owner (IOCL) shall have no liability in respect
thereof and the contractor shall not be entitled to raise
or include in the Final Bill any claims other than a
Notified Claim conforming in all respects and in
accordance with the provisions of Clause 6.6.3.0.
11.4 Clause 6.6.4.0 provides that no claim shall on any
account be made by the contractor after the Final Bill. It
further provides that any such claim shall be deemed to
have been waived and with respect to all such claims
not included in the Final Bill, the owner (IOCL) is
absolved and discharged, even if not including the same,
the contractor shall have acted under the mistake of law
or fact.
Thus, on a fair reading of the aforesaid provisions,
it can be seen that only those claims which are Notified
after following the procedure as referred to hereinabove
shall be considered as “Notified Claim” and in respect of
any claim other than the Notified Claim, the owner is
not liable to pay and as such is absolved and discharged
// 53 //
under the said clauses.
11.5 The next important clause is 6.7.0.0 with respect to the
discharge of owner’s liability. As per Clause 6.7.1.0, the
acceptance by the contractor of any amount paid by the
owner to the contractor in respect of the final dues of
the contractor under the Final Bill upon condition that
the said payment is being made in full and final
settlement of all said dues to the contractor shall,
without prejudice to the Notified Claims of the
contractor included in the Final Bill in accordance with
the provisions of Clause 6.6.3.0, be deemed to be in full
and final satisfaction of all such dues to the contractor
notwithstanding any qualifying remarks, protest or
condition imposed or purported to be imposed by the
contractor relative to the acceptance of such payment.
11.6 Clause 6.7.2.0 provides that the acceptance by the
contractor of any amount paid by the owner (IOCL) to
the contractor in respect of the Notified Claims of the
contractor included in the Final Bill in accordance with
the provisions of Clause 6.6.3.0 and associated
provisions thereunder, upon the condition that such
payment is being made in full and final settlement of all
the claims of the contractor shall, subject to the
provisions of Clause 6.7.3.0, be deemed to be in full and
final satisfaction of all claims of the contractor
notwithstanding any qualifying remarks, protest or
// 54 //
condition imposed or purported to be imposed by the
contractor relative to the acceptance of such payment
with the intent that upon acceptance by the contractor
of any payment made, the Contract (including the
arbitration clause) shall stand discharged and
extinguished insofar as relates to and/or concerns the
claims of the contractor.
11.7 The next important clause to be considered would be
Clause 9.0.0.0. The said clause is for Alternative
Dispute Resolution Machinery. As per Clause 9.0.1.0,
subject to the earlier Clauses, namely Clauses 6.7.1.0,
6.7.2.0 and 9.0.2.0, any dispute arising out of a
NOTIFIED CLAIM of the contractor included in the
Final Bill of the contractor in accordance with the
provisions of Clause 6.6.3.0 and if the contractor has
not opted for the Alternative Dispute Resolution
Machinery referred to in Clause 9.1.1.0 and any dispute
arising out of any Claim of the owner against the
contractor shall be referred to the arbitration of a Sole
Arbitrator. It also further provides that the owner may
prefer its Claims against the contractor as counterclaims if a Notified Claim of the contractor has been
referred to arbitration. It also further provides that the
contractor shall not, however, be entitled to raise as a
setoff, defence or counterclaim any claim which is not
a NOTIFIED CLAIM included in the contractor’s Final
// 55 //
Bill in accordance with the provisions of Clause 6.6.3.0.
11.8 Clause 9.0.2.0 is an exclusion clause by which, certain
matters are specifically excluded from the scope,
purview and ambit of the Arbitration Agreement. It provides that disputes or differences with respect to or concerning or relating to any of the matters
mentioned/specified in Clause 9.0.2.0 are excluded
from the scope, purview and ambit of the arbitration
agreement. It further provides that any such matter
which is specifically excluded viz. (i) with respect to or
concerning the scope or existence or otherwise of the Arbitration Agreement; (ii) whether or not a Claim sought
to be referred to arbitration by the contractor is a Notified Claim; (iii) whether or not a Notified Claim is included in the contractor’s Final Bill in accordance with
the provisions of Clause 6.6.3.0 and (iv) whether or not
the contractor has opted for the Alternative Dispute Resolution Machinery with respect to any Notified Claim included in the contractor’s Final Bill shall have to be decided by the General Manager prior to the arbitration
proceeding with or proceeding further with the reference
and the Arbitrator or the Arbitral Tribunal shall have no
jurisdiction to entertain the same or to render any decision with respect to such matters.
// 56 //
Thus, on a fair reading of clause 9.0.0.0, only the
dispute arising out of a NOTIFIED CLAIM of the contractor included in the FINAL BILL in accordance with
the provisions of Clause 6.6.3.0 shall be referred to arbitration, that too, subject to Clause 9.0.2.0 and any dispute / matter falling within Clause 9.0.2.0 shall have to
be first decided by the General Manager, including,
whether or not a Claim sought to be referred to arbitration by the contractor is a Notified Claim. Therefore, if
the claim is not a Notified Claim, as per Clause 6.6.1.0
and the same is not included in the Final Bill, such a
claim is outside the purview of the arbitration agreement. Whether or not a claim sought for arbitration by
the contractor is a Notified Claim or any such matter /
dispute is specifically excluded from the scope, purview
and ambit of arbitration agreement, such matter / dispute shall have to be first decided by the General Manager prior to the arbitral proceeding with or proceeding
further with the reference. Thus, unless there is a decision by the General Manager on whether or not a claim
sought to be referred to arbitration by the contractor is a
Notified Claim or not, the Arbitrator or Arbitral Tribunal
shall have no jurisdiction to entertain such a dispute.
The aforesaid clauses of the GCC are part of the
contract between the parties herein and both the parties
are bound by the aforesaid claims.
// 57 //
12. It is the case on behalf of the petitioner IOCL that the
IOCL had settled the claim of respondent – NCCL
accepting NCCL’s offer to grant extension of time; not to
give price adjustment of over 4% of the total contract
value and consequently IOCL condoned the delay of
1493 days and granted extension of time without
applying any price discount. Further for the delay of 65
days, IOCL applied the price discount of Rs.6,44,40,021
i.e. 4% of the total value of contract and thereafter IOCL
released the payment of Rs.4,53,04,021/ against
NCCL’s final bill (adjusting price discount of Rs.6.4
Crores as against Rs.14.8 Crores) and also returned
NCCL’s Bank Guarantee which came to be fully
accepted by the respondent NCCL. It is the case of IOCL
that thereafter, it was not open for the respondent to
raise any further claim. Therefore, it is the case on
behalf of the petitioner that, there being ‘accord and
satisfaction’ for the claim, being an ‘excepted claim’, it
was not open for the respondent to invoke the
arbitration agreement and request for appointment of an
Arbitrator. It is also the case on behalf of the petitioner
IOCL that in view of the specific decisions by the
General Manager, on “Notified Claims”, in view of Clause
9.0.2.0, for the same claims which are not held to be
‘Notified Claims’ by the General Manager, the matter
cannot be referred to the Arbitrator in view of the clause
pertaining to excluded matters.
// 58 //
On the other hand, it is the case on behalf of the
respondent that acceptance of the amount of
Rs.4,53,04,021/ was under duress and coercion. It is
also the case on behalf of the respondent that earlier
offer dated 02.11.2016 was a conditional one and was in
the nature of an offer and subsequently when the offer
was partially allowed, the respondent without any delay
communicated that the decision to partially allow its
application for EOT is unacceptable as the same is not
in accordance with the conditional offer given by the
respondent.
12.1 Now, so far as the General Manager’s decision on
Notified Claims is concerned, it is the case on behalf of
the respondent that even the decision of the General
Manager on the Notified Claims will always be subject to
the decision of the Arbitral Tribunal. By the impugned
judgment and order the High Court concluded and
summed up as under:
“81. Having regard to the foregoing discussion
hereinabove my conclusions can be summed as
follows:
I) Where there is contestation or the decision
rendered by the General Manager leaves scope for
argument as to whether the claims lodged by a
Contractor can be categorized as Notified Claims is best
// 59 //
left to the Arbitral Tribunal. In other words, except for
the situation where there is no doubt that the claims
were not lodged with the Engineer and the Site
Engineer as required under Clause 6.6.1.0 68 read
with 6.6.3.0 69, the matter would have to be left for
resolution by Arbitral Tribunal.
II) Aspects with regard to accord and satisfaction
of the claims or where there is a dispute will also have
to be left to the Arbitral Tribunal. The position in law in
this regard remains the same both pre and post
amendment brought about in the 1996 Act after
23.10.2015.
III) After the insertion of Subsection (6A) in 11 of
the 1996 Act the scope of inquiry by the Court in a
Section 11 petition, (once it is satisfied that it has
jurisdiction in the matter) is confined to ascertaining as
to whether or not a binding arbitration agreement
exists qua the parties before it which is relatable to the
disputes at hand.
IV) The space for correlating the dispute at hand
with the arbitration agreement is very narrow. Thus,
except for an open and shut case which throws up a
circumstance indicative of the fact that a particular
dispute does it not fall within the four corners of the
arbitration agreement obtaining between the parties
the matter would have to be resolved by an Arbitral
Tribunal. In other words, if there is contestation on
this score, the Court will allow the Arbitral Tribunal to
reach a conclusion one way or another. This approach
would be in keeping with the doctrine of Kompetenz
// 60 //
Kompetenz; a doctrine which has statutory recognition
under Section 16 of the 1996 Act.”
13. Having heard learned Counsel appearing for the
respective parties and in the facts and circumstances of
the case, the issue / aspect with regard to ‘accord and
satisfaction’ of claims is seriously disputed and is
debatable. Whether, in view of the acceptance of
Rs.4,53,04,021/ by the respondent NCCL which was
released by IOCL on the offer / letter made by the
respondent NCCL dated 02.11.2016 there is an instance
of ‘accord and satisfaction’ of the claims is a good and
reasonably arguable case. It cannot be said to be an
open and shut case. Therefore, even when it is observed
and held that such an aspect with regard to ‘accord and
satisfaction’ of the claims may/can be considered by the
Court at the stage of deciding Section 11 application, it
is always advisable and appropriate that in cases of
debatable and disputable facts, good reasonably
arguable case, the same should be left to the Arbitral
Tribunal. Similar view is expressed by this Court in the
case of Vidya Drolia (supra). Therefore, in the facts and
circumstances of the case, though it is specifically
observed and held that aspects with regard to ‘accord
and satisfaction’ of the claims can be considered by the
Court at the stage of deciding Section 11(6) application,
in the facts and circumstances of the case, the High
Court has not committed any error in observing that
// 61 //
aspects with regard to ‘accord and satisfaction’ of the
claims or where there is a serious dispute will have to be
left to the Arbitral Tribunal. However, at the same time,
we do not agree with the conclusion arrived at by the
High Court that after the insertion of SubSection (6A)
in Section 11 of the Arbitration Act, scope of inquiry by
the Court in Section 11 petition is confined only to
ascertain as to whether or not a binding arbitration
agreement exists qua the parties before it, which is
relatable to the disputes at hand. We are of the opinion
that though the Arbitral Tribunal may have jurisdiction
and authority to decide the disputes including the
question of jurisdiction and nonarbitrability, the same
can also be considered by the Court at the stage of
deciding Section 11 application if the facts are very clear
and glaring and in view of the specific clauses in the
agreement binding between the parties, whether the
dispute is nonarbitrable and/or it falls within the
excepted clause. Even at the stage of deciding Section
11 application, the Court may prima facie consider even
the aspect with regard to ‘accord and satisfaction’ of the
claims.
13.1 Now, so far as the submission on behalf of the
respective parties on the decision of the General
Manager on Notified Claims in Civil Appeal
No.341/2022 arising out of SLP (C) No.13161/2019 is
concerned, the General Manager has decided / declared
// 62 //
that the claims are not arbitrable since they had been
settled and the arbitration agreement has been
discharged under Clause 6.7.2.0 of the GCC and no
longer existed / subsisted. As observed hereinabove, the
claims had been settled or not is a debatable and
disputable question, which is to be left to be decided by
the Arbitral Tribunal. Therefore, matters related to the
Notified Claims in the facts and circumstances of the
case also shall have to be left to be decided by the
Arbitral Tribunal as in the fact situation the aspect of
‘accord and satisfaction’ and ‘Notified Claims’ both are
interconnected and interlinked.
13.2 Now, so far as the Civil Appeal No.342/2022 arising out
of SLP (C) No.13816/2019 is concerned, the General
Manager in exercise of powers under Clause 9.0.2.0 had
declared that none of the claims of the respondent is a
Notified Claim. From the communication dated
22.06.2018, it appears that the General Manager, after
elaborately dealing with all the alleged Notified Claims of
the respondent has thereafter found that none of the
claims made by the respondent is a Notified Claim. On a
conjoint reading of the relevant clauses of the GCC viz.
Clauses 9.0.1.0 and 9.0.2.0, the dispute arising out of
Notified Claims only, which is included in the Final Bill
of the contractor can be referred to arbitration. However,
as per Clause 9.0.2.0, any dispute or difference on
whether or not a claim sought to be referred to
// 63 //
arbitration by the contractor is a Notified Claim falls
within the excluded matters and the Arbitrator or
Arbitral Tribunal shall have no jurisdiction and/or
authority with respect thereto. The dispute or difference
whether or not a claim sought to be referred to
arbitration by the contractor is a Notified Claim shall
not and cannot form the subject matter of any reference
or submission to arbitration. Therefore, on a fair and
conjoint reading of Clause 9.0.1.0 and 9.0.2.0, it can
safely be concluded that (i) only the Notified Claims of
the contractor included in the Final Bill of the
contractor in accordance with the provisions of Clause
6.6.3.0 shall have to be referred to arbitration; (ii)
whether or not a claim sought to be referred to
arbitration by the contractor is a Notified Claim or not,
the Arbitrator or Arbitral Tribunal shall have no
jurisdiction at all; (iii) whether or not a claim is a
Notified Claim or not shall have to be decided by the
General Manager and that too, prior to arbitration
proceeding with or proceeding further with the
reference. Therefore, once the General Manager, on the
basis of the material on record takes a conscious
decision that a particular claim sought to be referred to
arbitration is not a Notified Claim, such a claim
thereafter cannot be referred to arbitration. The
language used in Clauses 9.0.1.0 and 9.0.2.0 is very
clear and unambiguous.
// 64 //
13.3 As observed hereinabove, parties to the contract are free
to agree on applicability of (1) proper law of contract, (2)
proper law of arbitration agreement and (3) proper law of
the conduct of arbitration. Parties to the contract also
may agree for matters excluded from the purview of
arbitration. As observed by this Court in a catena of
decisions, unless the effect of agreement results in
performance of an unlawful act, an agreement, which is
otherwise legal, cannot be held to be void and is binding
between the parties. At this stage, the decision of this
Court in the case of Sreekanth Transport (supra) is
required to be referred to. In the case before this Court,
the contract provided for exclusion of some matters from
the purview of arbitration. A senior officer of the
department was given the authority and power to
adjudicate the same. One of the clauses provided that
the decision of the Senior Officer, being the Adjudicator,
shall be final and binding between the parties. This
Court considered the same as ‘excepted matters’. In the
aforesaid decision, it is observed and held in paragraph
3 as under:
“3. “Excepted matters” obviously, as the parties
agreed, do not require any further adjudication since
the agreement itself provides a named adjudicator
concurrence to the same obviously is presumed by
reason of the unequivocal acceptance of the terms of
the contract by the parties and this is where the courts
have found out lacking in its jurisdiction to entertain
an application for reference to arbitration as regards
the disputes arising therefrom and it has been the
// 65 //
consistent view that in the event the claims arising
within the ambit of excepted matters, question of
assumption of jurisdiction of any arbitrator either with
or without the intervention of the court would not
arise; The parties themselves have decided to have the
same adjudicated by a particular officer in regard to
these matters: what are these exceptions however are
questions of fact and usually mentioned in the contract
documents and forms part of the agreement as such
there is no ambiguity in the matter of adjudication of
these specialised matters and termed in the agreement
as the excepted matters.”
13.4 In that view of the matter, the High Court has misread
and misinterpreted the clauses 9.0.1.0 and 9.0.2.0 and
has seriously erred in holding that where there is
contestation or the decision rendered by the General
Manager leaves scope for argument as to whether the
claims alleged by the contractor can be categorized as
Notified Claim is best left to the Arbitral Tribunal. The
dispute whether the claim is a Notified Claim or not is
specifically excluded from the scope, purview and ambit
of the arbitration agreement. Therefore, once such a
dispute falls within the ‘excepted matters’, any decision
by the General Manager on the issue of Notified Claims
cannot be the subject matter of arbitration proceeding.
13.5 Therefore, the High Court has erred in referring the
dispute to arbitration and appointing a sole Arbitrator to
adjudicate on the dispute with respect to the claims
which as such are held to be not Notified Claims by the
General Manager. Therefore, the Civil Appeal
// 66 //
No.342/2022 arising out of SLP (C) No.13408/2019 as
well as Civil Appeal Nos.343/2022 and 345/2022
arising out of SLP (C) Nos.13813/2019 and 13816/2019
respectively deserve to be allowed and the impugned
judgment and orders passed by the High Court in
respective arbitration petitions deserve to be quashed
and set aside.
13.6 So far as the Civil Appeal No.344/2022 arising out of
SLP (C) No.13815/2019 arising out of the impugned
judgment and order passed by the High Court in
Arbitration Petition No.407/2018 is concerned, as the
General Manager himself has declared that only one
claim of the respondent was / is a Notified Claim, the
said appeal is to be allowed partly by observing that the
claim which is declared by the General Manager as a
Notified Claim only shall have to be referred to
arbitration and the learned Arbitrator shall have no
jurisdiction to adjudicate the disputes with respect to
other claims which as such are not declared as Notified
Claims by the General Manager.
14. In view of the above and for the reasons stated above,
following order is passed.
(1) Civil Appeal No.341/2022 arising out of the
impugned judgment and order passed by the High
Court in Arbitration Petition No.115/2018 is
// 67 //
hereby dismissed. However, it is observed that the
learned Arbitrator shall first decide the aspect with
regard to ‘accord and satisfaction’ of the claims
and arbitrability of the disputes with regard to
such claims by deciding an application under
Section 16 of the Arbitration Act, which is reported
to be pending. The learned Arbitrator shall first
decide the jurisdiction of the Arbitral Tribunal and
the arbitrability of the claims within a period of
three months from the date of first sitting which
shall be within a period of one month from today.
All the contentions and/or defences which may be
available to the respective parties are kept open to
be considered by the learned Arbitrator in
accordance with law and on its own merits and
considering the relevant clauses of the contract
and the material on record.
(2) Civil Appeal No.342/2022 arising out of the
impugned judgment and order passed by the High
Court in Arbitration Petition No.356/2018 is
hereby allowed. Impugned judgment and order
passed by the High Court in Arbitration Petition
No.356/2018 referring the dispute between the
parties to arbitration and appointing the Arbitrator
is hereby quashed and set aside.
(3) Similarly, Civil Appeal No.343/2022 arising out of
// 68 //
the impugned judgment and order passed by the
High Court in Arbitration Petition No.116/2018
and Civil Appeal No.345/2022 arising out of the
impugned judgment and order passed by the High
Court in Arbitration Petition No.406/2018 are
allowed and consequently, the impugned
judgments and orders passed by the High Court in
Arbitration Petition Nos.116/2018 & 406/2018 are
hereby quashed and set aside.
(4) So far as Civil Appeal No.344/2022 arising out of
the impugned judgment and order passed by the
High Court in Arbitration Petition No.407/2018 is
concerned, the same is partly allowed. The
impugned judgment and order passed by the High
Court in Arbitration Petition No.407/2018 is
hereby modified to the extent and it is directed that
only one claim of the respondent which is declared
by the General Manager as a Notified Claim shall
have to be referred to arbitration and the learned
Arbitrator shall adjudicate only that claim which is
declared by the General Manager as a Notified
Claim and the learned Arbitral Tribunal shall not
have any jurisdiction to adjudicate on any other
claims which as such are not declared as Notified
Claims.
In the facts and circumstances of the case,
// 69 //
there shall be no order as to costs.
……………………………….J.
[M.R. SHAH]
……………………………….J.
[B.V. NAGARATHNA]
NEW DELHI;
JULY 20, 2022.
Comments
Post a Comment